SCHOOLS
The Board
of Education
First to be
called upon, the "B.O.E." made their pitch. Financial figures were
supplied by the Director of Finance of the B.O.E. regarding ten year regular
budget costs looking "forward" ten years. Construction cost was presented
by the Chair. and the Board Member who had sat on the Select Team.
Bottom line: $65 million NET.
The School
Building Committee
Following
the Board of Education came the School Building Committee; the Chair. of
this official Committee specifically called out gross (we think) numbers
for other construction:
HIGH SCHOOL
- $36,793,480
NEW 3-4-5
- $27,978,275
MIDDLE SCHOOL
- $3,279,562
EAST&SOUTH
HOUSES - $10,246,795
SCHOOL ROAD
(to reconfigure) - approx. $1,500,000
_______________________________
TOTAL -
$79,798,112 GROSS (NET total $3.2 million higher than Board of Education
number)
The Select
Team
The Co-Chair.
of this Ad Hoc Committee reported on their supporting activities, including
the "Impact of Town Operating Budget and School Expansion Debt Service
Costs" document (dated August 15, 2001). This group is intending
to develop informational tools regarding the items that will ultimately
go to Referendum.
SEPTIC SYSTEMS
Click HERE
for background on this issue.
The Select
Committee on the Impact of Sewage Treatment on the Character of Weston
was not present. Information was given by the First Selectman that
the consultant had submitted a report stating that $2.4 million to $2.6
million was the cost of completely redoing (including recycling and
tertiary treatment) - although the Department of Environmental Protection
had not approved the final details of the full construction of systems
and other treatment structures in the program yet. The higher figure
represents recycling of water at the new building (we think).
PARKS &
RECREATION
"About Town"
had had enough by this time (@10:30pm); the Parks and Recreation
Commission spoke of the shifting use of fields - and how many would be
lost during construction. Plans for Bisceglie and Morehouse Farm
Park (Minerva Heady's land) and school campus total $10.5 million. Of
this larger total,s as a subtotal amount, are plans for...2 little league
fields, 3 multi-use fields, 2 tennis courts (is that enough?) and concession
stand, lighting of 2 athletic fields, playground, nature trails and board
walks, overlook (great view), water supply--and a SKATE PARK come to...$4.2
million (subtotal). And some more items. Breaking down
these numbers further, according to written material available at the door,
fields at Bisceglie for school and adult use (softball and baseball) might
come to $400,000. The big loser in all the plans is
tennis (six courts lost on School Road)...does this make sense to you?
---------------------------------------------------------------------------------------------------------------------------------------------
The bottom line? "About Town" counted maybe $93 million gross to do it all. But what do I know?
Next step is for the Board of Selectmen to recommend a number (and the projects to be included, we presume)...