
Above, Building Committee (2006) reviews Town Hall roof drawings.
Building
Committee/School Building Committee:
External links scrubbed to avoid bad ones and really bad ones.
CONTENTS OF THIS PAGE
INCLUDE...
TIMELINE
BUILDING COMMITTEE-SCHOOL
BUILDING COMMITTEE OLD NOTES - back to May
2000;
DISCUSSION
OF SCHOOLS/FIELDS MASTER PLAN AND BID SCHEDULE - October 2003;
SPORTS
COMPLEX

TIMELINE -
PHASING OF CONSTRUCTION A WORK IN PROGRESS...
The big question-marks:
- Tertiary treatment
plant completed and working...when;
- Availability of
fields for sports teams to practice and play, in Weston, this coming
school
year;
- Will the whole
project stay "on budget" and "on quality" (and, by the way, "on time")?
- Since there will
be banging and clanging at the high school for a few years, year-round,
it is imperative that "swing space" be available (in the new 3-4-5
building)
to handle emergencies, ie overflow for escaping noise and fumes, etc.,
if that turns out to be necessary.
- Also, please note
that Middle School projects have slipped and redesign will most likely
be needed for the new auditorium for that facility. Early
estimates
by F-T for building the design were double the amount in the Referendum
for this building project.
- What about
the Sports Complex?
OLD
NOTES...
SCHOOL BUILDING
COMMITTEE AT BOARD OF FINANCE SPECIAL MEETING ON CAPITAL BUDGET
TUESDAY,
MARCH 4 at 8pm in TOWN HALL MEETING ROOM (on Channel 79) - CONSIDERED A
CONTINUATION OF CAPITAL BUDGET DISCUSSION, BEGUN WITH BOARD OF
SELECTMEN:
After full
report from Owner's Rep on discussions he has had with Westport-Weston
Health District and the S.F.U. of the State Board of Education, project
can continue if Town of Weston is serious about repairing water system
defects (if any) and installing new, second well (with connecting
piping
to new and old facilities/circulating systems) where necesssary--after
sufficient professional study and design (this is "About Town's"
interpretation).
Also, letter from CTDEP does not, in the opinion of at least one of the
members of the Board of Finance, recognize our water conservation
efforts.
SCHOOL BUILDING
COMMITTEE MEETINGS CANCELLED for FEB. 19 and SUB-COMMITTEE on FINISHES
for FEB. 26; MARCH 5 SCHOOL BUILDING COMMITTEE MEETING
CANCELLED...TO
ATTEND CONSERVATION COMMISSION TOGETHER.
School Building
Committee/Building Committee/DESIGN SUB-COMMITTEE, Wednesday, February
12, 2003 at 7 pm (one-half hour earlier than normal):
LOCATION
IS A NEW PLACE - FIREHOUSE MEETING ROOM (we assume this is the MAIN
FIREHOUSE
in the Town Hall Complex--UPSTAIRS)
AGENDA
Minutes/done.
Invoices/done
- new Excel spreadsheet for monitoring referendum $$ used and
distributed.
Water Supply System
engineering firm selection/discussion of WWHD and DEP, DPH
communications
(State of CT closed for Lincoln's Birthday [actual]) regarding need for
study of second well, distribution system; timing re: school
construction
(no delay filing early papers--work should be on-going for approval of
next phase steps);
DESIGN SUBCOMMITTEE:
at 7:30pm Fletcher-Thompson presentation to sub-committee of 3-4-5
school
and high school interior lighting and continuation of sight
lighting/"3-4-5"
school lighting discussed first ("About Town" did not stay past 9pm)
and
showed that each fixture will be reviewed for placement, overall
selections
coordinate with architecture--and, we note, the "Dark Night Sky"
proposals
in the legislature this session relate to this project, perhaps!
DESIGN SUB-COMMITTEE WORKS OVERTIME: MEETINGS CONDUCTED AFTER
REGULAR
SCHOOL BUILDING COMMITTEE SESSIONS THE NEXT FOUR MEETINGS.
Adjourn
School Building
Committee/Building Committee, Feb. 5, 20003, 7:30pm, Weston Library
AGENDA
Approve minutes/we
were not present at this point
Approve invoices/ditto
Review studies
and design (engineering proposal) for Campus water supply system*
Relocate modulars
to High School**
Chair. to discuss
sub-committees
Fletcher-Thompson
to discuss lighting design (interior) - of all buildings, or just the
high
school?***
* = rescheduled
for next week (Town Engineer had to attend Budget Meeting)
** = we are
not sure this matter was covered
*** = full
presentation next week--"design meeting" at 6:30pm, regular School
Building
Committee, including lighting matters, 7:30pm.
School Building
Committee/Building Committee, Wednesday, January 29, 2003, 7:30pm,
Commission
Room
AGENDA
Minutes/OK
Parks and Rec
request to relocate trees at Morehouse Farm Park/no decision - further
discussion
Fletcher-Thompson
proposal for Xenon/Fire pump building/vote to proceed
Allen Swerdlowe
to discuss Booster Barn/meeting report
Schedule for F-T
presentations of lighting finishes, etc./"About Town" left before this
discussion, but not before timing of approvals came up - many OK's
coming
in the next few months, including need for resolution of need for
second
well and water system/lines to meet State Standards (no new buildings
on
campus OK'd by S.F.U. until past problems resolved).
School Building
Committee/Building Committee, Wednesday, January 22, 2003,
7:30pm,
Commission Room
AGENDA
Minutes/no action
Parks and Recreation
request to relocate trees at Morehouse/no action
Review application
material to be presented to the Conservation Commission for the School
Campus/briefly, draft version discussed.
O&G will present
preliminary interior phasing plan for the High School construction
project/draft
discussed--apparently, phasing and timing of High School improvements
and
new construction will put the status of W.H.S. from October 2003 until
December 2005 very much in an upset mode (anyone for air quality
measurement)?
The new sections at W.H.S. will come first, linkage passageways between
old sections to be constructed in a timely and, we presume, temporary,
fashion.
School Building
Committee/Building Committee, January 15, 2003, 7:30 pm, Commission
Room
at Town Hall ("About Town" left at 10pm, before meeting ended--items
were
taken somewhat out of order as design review taken early).
AGENDA
Minutes/OK
Parks&Rec.
request to proceed with play fields investigation/$45,000 OK'd
Invoices for approval/not
all OK'd--but most important, it was moved and seconded to have the
Chair.
of the Committee and the Owner's Rep make payment
decisions/recommendations--we
do not have clear whether the School Building Committee delegated all
powers
in this matter to the two individuals or not...when bills are
submitted,
what is the exact procedure? (Perhaps the official minutes will explain
this); Owner's Rep also brought up need for organizational
meeting
prior to "receipt of application" of School Road Site Plan
(disturbance/improvement)
for Conservation Commission review/Public Hearing.
Select peer review
firm/was not present for this
Fletcher-Thompson
proposal for Xenon/fire pump building design/discussed.
Continuation of
Site Plan presentation/discussion about lighting, planting near tennis
courts.
School Building
Committee/Building Committee, January 8, 2003, 7:30pm in the Commission
Room at Town Hall
AGENDA
1. Approval
of minutes/done
2. High
School Fire Alarm System/vote to approve Fletcher-Thompson fee
($23,000)
for design of fire alarm system for existing high school ASAP--not to
come
out of bond issue funds; much discussion about how to best
accomodate
Superintendent's wish to fix this safety problem without further
delay.
First Selectmen to get request for these additional funds.
3. School
Campus Site and Landscaping Plan presentation/civil engineer and
landscape
designer presentations; there was some debate about fencing
around
the "Sports Complex" as well as concern about landscaping protection
for
the site of two new tennis courts. "About Town" left at 10:15pm
while
discussion was still ongoing.
School Building
Committee/Building Committee, Dec. 18, 2002, Town Hall Commission Room,
7:30pm
AGENDA
1. Call
to order (verification of quorum of both the Building Committee and the
School Building Committee)/eventual quorum of both groups;
recognition
of service to former secretary (Town Clerk) for outstanding service for
many years.
2. Minutes
approval/done (when quorum appeared);
3. Town
Engineer report on Middle School floor drains (capital budget
proposal)/next
phase of testing to go on--two bids in hand, another to come;
4. Board
of Education proposal for reliable fire alarm system at Weston High
School/action
put off until other Building Committee members can review this item in
the near future. F-T reports on how a new fire alarm system will
work into the old and new parts of W.H.S.--very little of this "hard
wired"
solution would have to be relocated after construction of school
addition-renovation
took place.
5. Fletcher-Thompson,
O&G presentation of reconciliation of high school addition cost
reductions/over
budget by a small %, as best as can be determined, at this stage, and
that
amount will be affected more by the cost of high school renovation
"surprises"
than anything else (NOTE: THIS IS "ABOUT TOWN'S"
UNDERSTANDING
AND IS NOT OFFICIAL); "construction documents" phase to begin
for 3-4-5 school project (quorum votes to do this and the next
item--unanimously);
"construction documents" phase to begin, as well, for high school
project,
once detail on some fenestration is resolved no later than the next
School
Building Committee session January 8, 2003.
School Building/Building
Committee, Wednesday, December 11, 2002 at 7:30pm in the Commission
Room
at Town Hall
AGENDA
1. Election
of Officers/Richard Wolf, Chair., Joe Fitzpatrick, Vice-Chair.
2. Minutes/OK
3. Owner's
Rep report - invoices/some OKd, some not (either questions about format
or relation to actual budget expenditures so far)
4. Committee
to present cost savings for 3-4-5 school/suggestion to cut out some
design
features not put in for functionality.
5. Fletcher-Thompson
and O&G present design development cost estimates for High School
and
site work/F-T shows we are close to bonding number; O&G shows
more overage. NOTE: still need clear understanding of where
Parks and Recreation improvements fit into on-Campus improvements (are
these facilities being counted twice, or left out altogether--"About
Town's"
comment).
School Building
Committee, WEDNESDAY, DEC. 4, 2002, 7:30pm IN WESTON LIBRARY:
With a quorum
present (Wolf, Swerdlowe, Fitzpatrick, Coprio, Stuebe, Pierson;
Gary
across the parking lot at Conservation Commission, discussing tertiary
treatment).
1. Approval
of minutes/done
2. Presentation
and discussion of 3-4-5 school design development cost estimates by
O&G
and Fletcher-Thompson/over by @2 to 3%.
3. Discuss
wall and fence types/still going on when "About Town" left at
9:30pm.
NEXT WEEK - site work and high school design development estimates,
plus
recommendations on 3-4-5 school (Dec. 18 is the time for construction
documents
phase to start...)
School Building/Building
Committee Wednesday, November 20, 2002, Town Hall Commission Room -
7:30pm-9:50pm
AGENDA
1. Minutes/approved
2. Soccer
field resurfacing design proposal from Barry Blades/$17,500 proposal
3. OWNER'S
REP REPORT:
- Invoices/most
approved - need for double-check with Parks and Rec on one...
- Cost Reports/format
for tracking progress of projects, filing already paid invoices in the
proper slots still a work in progress.
- Mechanical/Electrical
systems/put off for another time
- Dates for estimates
extended to two days: Dec. 4 new 3-4-5 school; Dec. 11 now
date for high school additions and site work for all of School Road.
School Building
Committee
AGENDA, 7:30pm
in the Library Nov. 6
Minutes/approved
Soccer Field
presentation from Sports Complex leader and athletic director/excellent
case made for proceeding with School Road resurfacing for all-weather
soccer
field--over-used now, and during years of construction, fields will be
at a premium
Owner's Rep
report (budget control report)/format shown.
Adjourned
at 9:35pm
School
Building Committee (SBC) - and Regular Building Committee (BC),
Wednesday,
October 30, 2002, 7:30pm-10:25pm, Commission Room at Town Hall
AGENDA
1. Approval
of minutes (SBC)/done
2. Owner's
Rep report/some bills paid, some deferred for later meeting;
NOTE:
under this agenda item were discussed matters of great importance to
the
Town--update on progress of septic solution, discussion of the SFU role
(we have to make sure every "i" is dotted and "t" crossed).
3. Proposal
for resurfacing soccer fields (BC)/School Building Committee members
participated
in discussion; motion/second from Building Committee members
(quorum
present) to send letter to Board of Selectmen for presentation at 8am
meeting
Thursday, Oct. 31, 8am, to hold up on this matter until impact on all
three
parts of the Referendum and timing schedule has been comprehensively
reviewed
and no negative impacts to the school part of the program can be
assured
("About Town's" wording--NOT OFFICIAL). This relates to (scan
down
the LWV of Weston OBSERVER page) special multi-Board
meeting.
4. Parks
and Rec discussion of relationship between Parks and Rec and School
Building
Committee/done, very helpful.
5. Hurlbutt
Window Replacement (BC)/this is the big, beautiful window in the
cafetorium
of South House, so lots of care to detail being taken (funded in
previous
budgets)
6. Invoice
- H.S. Auditorium lights (BC)/discussed under item #2--we think they
voted
to pay it (?).
7. 3-4-5
School design workshop (SBC)/this item taken earlier in the agenda as a
courtesy to architects and construction manager; architects
officially
offer to design "Booster Barn" to all codes in order to be sure the
design
work on Weston High School renovations and the new 3-4-5 school are not
compromised--and also because the School Building Committee site
planning
efforts have come up with such a good result (it would be really ugly
to
have discordant element in such an import place on the newly renovated
Campus); brick discussion, finer detail (larger scale drawings).
School Building
Committee, Wednesday, October 23, 2002 at 7:30pm in the Town Hall
Commission
Room.
AGENDA
Approval of
the minutes of past meeting/OK'd
Owner's Rep
report/BILLS: to Triton Environmental, OK, to Frederick Clark
Assoc.--held
for re-evaluation (checking our own records), to Angus MacDonald
(disussion,
OK'd).
Site Plan
Update, 3-4-5 school/3-4-5 site plan refinements (to be continued)
Booster Barn
discussion/design challenge now that it is to be in a prominant
location.
High School
Design Workshop/continued discussion of design detail--particularly,
grading
impact on main building entry...is there one?
School Building
Committee, Wednesday, October 16, 2002 at 7:30pm, Town Hall Commission
Room (or if not there, in the Library?)
AGENDA
Approval of
the minutes/done;
Owners Rep
report:second well needed--must get Selectmen to address this matter in
FY04 budget (Leggett, Brashears & Grahm study for P&Z yr2000
reviewed);
technology consultant to be hired; $135,000 remaining in bonding
for water conservation and septic/sewer committee work;
Invoices -
Triton/further mapping needed for full A-2 picture on school campus
(?)--work
on Morehouse Farm Park has never gone through the School Building
Committee
yet;
Design Issues-3-4-5
school/model shown (to be presented at Kiwanis this Saturday) and
design
critiqued...
School Building
Committee, Wednesday, October 9, 2002 at 7:30pm, Town Hall Commission
Room
AGENDA
- Minutes approval/done,
OK
- Owner's Rep report/report
on subjects for meeting to be held with W.W.H.D.(second well?), fire
safety
discussions with Fire Marshal office
- Discussion/approval
Technology Consultant Proposals/evaluation of technology consultant
responses
to RFP (take two lowest) by Owner's Rep and others, if needed--decide
on
selection for the School Building Committee.
- Continuation of
design workshops on 3-4-5 and high school/done
- Vote
taken to approve site plan for campus ("About Town" assumes that this
is
for the purpose of submissions to Conservation and Army Corps @end of
year
into early '03), dated map presented at this meeting, plus
understanding
that footprint of W.M.S. auditorium might get smaller.
School Building
Committee for Wednesday, October 2, 2002 at 7:30pm in the Weston
Library
Community Room:
AGENDA
- Minutes of September
25, 2002: approved;
- Owner's
Rep report--bills, etc. (borings, add cost of airconditioning;
discussion
of WWHD reminder on second well for Town-School use) - to be paid;
report
on office space in Jarvis project;
- Hurlbutt part
of Bond items changed to $362,810, (down from @$1 million): this
revision has removed new drive at School Road, we think, added more
parking,
turned bus loop/queuing into snake shaped road close to softball field
(with possibility of double+ queue in Bus Garage area) - approved 5-1-1
(five in favor, one opposed, one abstention);
- Preliminary Grading
Plan: more detailed drawing shown, not finished yet--main thrust is to
minimize intrusion into wetlands. Neighbor comments on overly
close
school building and lack of response, in his opinion, to request to
move
3-4-5 building as far as possible from his property line;
- High School Design
Workshop continues;
- "About Town" left
(after 10pm) prior to completion of the last mentioned item (or "Any
other
business...").
School Building
Committee, Wednesday, September 25, 2002, 7:30pm (we left at 10pm,
Design
Workshop winding down) in the Town Hall Commission Room.
AGENDA
Minutes of
Sept. 18, 2002/OK; Invoices/paid; 3-5 Elementary School
Design
Workshop/took place; Any other business: neighbor of 3-4-5
school brought engineer and lawyer's letters asking that new building
be
set back further from his property.
On an additional
item ("any other business?"), Town Administrator and "Owner's Rep"
propose
to BUILDING COMMITTEE members improvements to the second floor of the
Jarvis
Military Academy for use as offices for Owner's Rep and the
Conservation
Planner, at a cost of $28,988. Building Committee makes
suggestions
re: heating/airconditioning approach, we think ("About Town" not
known for construction hands-on prowess).
School Building
Committee, Wednesday, September 18, 2002, Town Hall Commission Room,
7:30pm
AGENDA
Approval of
the Minutes/done
Invoices approval
(not all OK'd), Elementary School bid discussion-approval/done although
only one bid returned,
Bus Barn Relocation
services proposal: Fletcher Thompson/strong opposition to
diverting
attention and funds from main projects authorized by Town Meeting--if
money
came from another source than the $79 million bonding, this activity
could
be accomplished.
Technology
Consultant services: Design Development phases/ letter read from
school Techology person--School Building Committee OK with this
proposal
as described by Owner's Rep., 3-4-5 Elementary School and High School
Design
Workshop/we left at 10:35pm.
Special School
Building Committee DESIGN WORKSHOP on Weston High School Design
Development
Town Hall Meeting Room, Thursday, September 12, 2002 at 7:30pm; AGENDA
includes approval of minutes, also.
School Building Committee Wednesday, September 4,
2002,
7:30pm, Town Hall Commission Room--ALL 10 MEMBERS PRESENT (plus 3
members
of Board of Education in audience, Director of Finance for
schools;
neighbors of 3-4-5 and Sports Complex present. Owner's
Representative
on board! (Harold Mindel [?]).
AGENDA (finished
before 10pm)
Minutes of
August 28, 2002/OK; Question about Fire Marshall's request for
more
storage space in 3-4-5 brought up--answer next week; Site Plan
Updates/new
plan has track flipped, tennis courts (6) in same general area (some
same
as exist); 3-4-5 Design Development progress drawings/will be
available
in smaller size in Town Clerk's Office; High School Design
Development
progress drawings/fenestration, design of roof of gym fitting into
overall
design discussed.
School
Building Committee Wednesday, August 28, 2002:
AGENDA and
unofficial report.
- approval of minutes
done;
- Chair. announces
that "Owner's Representative" will come on board next week (according
to
discussion with First Selectman);
- middle school
pump, roof drains (John Conte gave report - Superintendent reported
that
everything was impressively done, thanks to Town of Weston and Town
Engineer);
- detailed review
of project architectural and construction schedule - still a draft, but
Construction Manager's (O&G) only warning is decision must be made
by end of September on what is going to happen with Middle School
Auditorium
- O&G reports on this and the major items in the schedule.
- Discussion of
where we stand on presentation to Army Corps, DEP And Conservation
- P.S. notice how
much it is raining lately? As Martha would say, this is a GOOD
THING.
School
Building Committee Wednesday, August 21, 2002, 7:30pm, Town Hall
Commission
Room
AGENDA - Approved
minutes; Middle School Ejector Pump (done), drainage project to be
discussed
next week; Discussion of role of Facility Manager/Weston Schools
- not really discussed (both Board of Education and Building Committee
want a better experience with communication and implementation of these
projects than has been done before); Design Development drawings of
high
school project begun--window spacing, roof lines reviewed; middle
school auditorium cost savings--Board of Education will work on this
some
more this coming week.
School
Building Committee - Wednesday, August 14, 2002 at 7:30pm-@9pm,
Commission
Room:
AGENDA/what
was accomplished:
- "Set time for
future meetings";/not done until summer vacationers return.
- report on East
House and South House window replacements;/bills reviewed
- revised cost summary
for the high school;/done - go-ahead given for next stage ("Design
Development")
by 5-1 vote.
- revised cost summary
for the 3-4-5 school;/school moved further from Sports Complex as high
school gym gets a tad smaller.
- partial "VE" items
for the middle school (what does "VE" stand for? VALUE ENGINEERING!!!)
- any other business
that should properly come before the committee./discussion of overall
assessment
of who is responsible for what; question from Parks and
Recreation
Commission about status of fields and playing courts' share of bonding
budget--have there been revisions?
School
Building Committee - Wednesday, August 7, 2002 at 7:30pm until 11pm in
Community Room at Weston Library. Agenda included, and summary of
what traspired written for each of three items; neighbors attend
plus 9 of 11 School Building Committee members (plus First Selectman,
High
School Principal, architects, construction manager):
- review of site
plan for alternate field location on "school campus road" - alternate
selected
that keeps best separation from Parade Ground Court (on all sides)
while
preserving green space between new 3-4-5 School and Weston High School
- Middle School
cost reductions - commitment by Board of Education waits for full
discussion
at that Board, but big overage demands that something be done
- 3-4-5 school and
High School development - detailed drawing continuing, savings being
found
as closer design efforts make calculated and intelligent choices.
School Building
Committee - July 31, 2002. Neighbors of the Sports Complex came
and
told the School Building Committee in no uncertain terms of their
displeasure
with the above proposal as it affected the livability of their
properties
(the property line setback more than half the distance that, in a
similar
project in Fairfield, neighbors had prevailed in legal opposition two
years
ago - summary from lexis.com, submitted by neighbor). After
"pruning,"
high school budget still $2 million above Referendum number.
Discussion
ensued after 10pm on the subject of School Building Committee response
to all neighbors located near school and sports projects.
School Building
Committee - July 24, 2002, Wednesday, WORKSHOP with the Board of
Education
reviews cost savings for 3-5 building and site development at 7:30pm in
the Town Hall Commission Room. "List of Cost Reduction Items" for
3-4-5 and site development as well as high school had goals for
reduction,
as listed on O&G 7/24/2002 document and simplified for viewing
audience
as: $4,666,479 for High School and $673,119 for 3-4-5 school (and
concomitant site work) . After three hour+ meeting, these goals
had
not yet been achieved (because the Committee had not gotten to the High
School yet); more next week on high school and middle school
(7:30pm
Wednesday, July 31).
School Building
Committee, Wednesday, July 17, 2002, 7pm, Town Hall Meeting Room:
AGENDA:
7pm - Owner's
representative #3 interview - Committee makes decision but this WEBpage
will not reveal the choice out of courtesy to Town of Weston Building
Committee.
7:40pm - South
House Roof - Committee decides what they think is the best solution and
votes to recommend this action (I don't really have the background to
say
exactly what they did)
7:45pm - Conservation
Commission report from CC Chair. - this was done first - lots of
meeting
time ahead for School Building architects, construction managers,
owner's
rep and Committee to get projects passed by CC (editorial opinion)
8:15pm - O&G/FT
report on School Project Estimate - down to $8 million overage (agreed
upon by architect and construction manager and their cost estimators)
Denied
without prejudice, the Town of Weston can reapply for Conservation
Commission approval for use of Bisceglie Park - or some other place, or
some other concepts. The reasons given were:
- Feasible and prudent
alternatives for constructed or conventional septic fields on the
designated
site or other sites were not adequately examined.
- The application
was incomplete because the applicant did not present a public health
certificate
for the constructed septic system and did not adequately explain why it
was not available.
- The application
was also incomplete because it did not adequately address protection of
a Class A river and associated wetlands from water and effluent runoff
and the use and effects of fertilizers and pesticides by providing
examples
of working systems (constructed septic field, ball fields and parking
lot)
under similar environmental conditions.
School
Building Committee Wednesday, July 10, 2002 at 6:45pm in the Weston
Library
Stacks area:
AGENDA - at
6:45pm, Interviews of two of three candidates for owner's
representative;
8pm, Discussion of cost estimates for the project. Reports by
O&G
and Fletcher-Thompson (highlights from summary sheet prepared by
O&G):
Referendum
estimate:$79,435,000
- at the July 10 School Building Committee, attended by First
Selectman,
Selectman, Chair of the Board of Education, and 10 of 11 members of the
Committee, recriminations for Conservation and DEP problems
surface;
architect and construction manager soldier on; next week the
meeting
will be a discussion of reconciled estimates
Fletcher-Thompson
estimator says total cost is $81,247,057
O&G estimator
says total cost is $89,728,379
School Building
Committee Wednesday, June 26, 2002 at 7:30pm in the Commission Room at
Town Hall...
AGENDA includes
- reports on Bisceglie project, South House roof, DEP status, revised
High
School facade, revised 3-4-5 site plan
School Building
Committee, 7:30pm, June 19, 2002, Commission Room at Town Hall
AGENDA...with
a quorum present, the following items were discussed and acted upon:
- Approval of minutes
of June 12/done
- Discussion of
proposal to move the bus garage/interesting to see how creative
solutions
to School projects may coordinate with a better plan
- Discussion of
lighting and drapery contract, WHS auditorium/second bid received,
first
bid better for Town - vote to send along this news to contractor and
School
Administration and staff and proceed -
- South House roof
report - nothing new
- Bisceglie Park
report, Parks and Recreation Commission - this discussion took place
first,
and became a far-reaching discussion of how Item #1 from the Referendum
might end up shifting funds within the original
- High School Facade
update - Fletcher-Thompson - not done
- 3-4-5 school site
plan report - Fletcher-Thompson - not done
School Building
Committee (June 12) in the Stacks of the Weston Library:
PRESENT:
Richard Wolf, Joe Fitzpatrick, Don Gary, Doug Steube, Ellen Uzenoff,
Dave
Coprio, John Cunningham (left at 8pm), Frank Lupo, Allan Swerdlowe,
Michael
Greenberg (100% of the membership); Cynthia Williams; WHS - Mary Kolek,
ass't; Hurlbutt - Dr. T; WMS - Darli Ebling; Board of Ed -
Barbara Ford, Laura Smits, Les Wolf; Bob Atkinson (left at
8pm-returned
later), Board of Finance; Doris Fiotakis (Drama, WHS) plus sound
contractor; neighbor, Parade Ground Court; CONSULTANTS included
O&G
rep, Blades&Goven (2), Fletcher-Thompson (5), and "About Town."
This meeting
took from 7:30pm until around 10:30pm. Held in the "Stacks" at
Weston
Library on a busy night for meetings, First Selectman Woody Bliss and
Town
Administrator Tom Landry dropped in to consult about WHS sound system
issue
- report next week on what happened after Town Attorney was consulted
about
need for competitive bidding on this project.
ACTION:
Invoices for
design work were approved totally $253,700.50 (for work done between
March
16 and April 30) - please see official minutes for which items are what
% complete, as well as who moved and who seconded this motion.
MEETING SUMMARY
(unofficial, of course):
WHS plans
were reviewed. For the whole School Road series of projects, July
10 will be when Design Development starts. There are overages on
consultant fees and $$ for owners representative. Discussion took
place about "ED SPECS" and which were funded in the Referendum and
which
had to be revised to meet the $79 million total in the Referendum cost
estimate. The new 3-4-5 lower middle school was presented along
with
studies of how to move the building, the bus lane and turnaround and
then
the parking for alternate 'B' and 'C' to satisfy both the neighbors on
Parade Grount Court as well as keeping a "Greensward" and not a parking
lot, as the view out of school rooms.
The Weston
High School Auditorium issue then arose. As noted above, there is
more to come on this next week. The Weston Middle School
Auditorium
budget has been scaled back in size approximately 4000 sq ft (fewer
seats)
and the extra music-associated rooms and other related renovations put
in the first Referendum item's budget (we think) in order to reduce the
large overage estimated for this project. This project in its new
form will have estimated made now by O%G.
Special
Town Meeting on 16 Parade Ground Court (May 30, 2002):
It was so
close that a few votes would have made a difference. Many
questions
were asked, statements made (especially interesting was a previous "no,
no, no" voter saying he was going to vote "yes" to keep the previously
expressed "will of the majority" going forward).
It is the opinion
of this WEBpage that the turning point came when the Chair. of the
School
Building Committee and the Board of Education member on that body spoke
clearly and eloquently in favor of the purchase. One of the
particular
details of this Town Meeting was the introduction of a League of Women
Voters idea to call for a secret ballot (made at this meeting by, we
think,
a PTO "SCOOP" representative).
There were
two (2) votes taken, however. The first, the traditional way, was
for the issue to be decided on a "standing count" on the item before
the
meeting related to 16 Parade Ground Court (or, in more archaic
terminology,
"I call for a division of the house"). The first vote required
Town
Meeting to stand and vote "yes" or "no" on whether to have a "standing
count" on the main question or not. It failed by a 78 ("NO")-53
("YES")
vote.
The meeting
proceded to take a secret ballot on the main
question
("yes"
was in favor of purchase of 16 Parade Grount Court and to take the
funds
from the already approved $80 million Bond Issue). After sending
the Town Meeting voters to three (3) different locations in the Weston
Middle School cafeteria by street in alphabetical divisions, a simple
"yes"
or "no" sheet was filled out or checked off and given to the Registrars
and Special Assisitant Registrars at the three locations by the voters
inserting the small piece of paper in a wooden box. After this
took
place, many people left, not waiting for the results tobe
tallied!!!
But the results came promptly, before 10pm. They were: 81
"YES"
and 64 "NO" - the main motion passed.
NOTE: What
this tells "About Town" is that those at Town Meeting were present to
show
support for their neighbors in public, but to vote in favor of the
school
project and thus against their neighbors on a secret ballot. And
there are other reasons as well.
Fourteen (14)
people did not vote on the first motion who voted on the main motion by
secret ballot...who were these voters? They did not want to stand
up and be counted voting against the administration or PTO (i.e. had
the
first count passed, and a standing vote had been taken - and the main
motion
had failed, it is presumed that a motion for reconsideration and a
secret
ballot would have been made anyway. And that vote would
have
been "YES" on the main motion.)
School Building
Committee, Wednesday, May 29, 2002, Town Hall Commission Room, 7:30pm
A short agenda
but a long meeting; Nature Center Ad Hoc Committee brings forward
architect contract for review for Lachat Property development as
education
center/entry to The Den. High School Auditorium Lighting
discussed
re: how this project, OK'd at ATBM, will be bid out and completed in a
timely fashion. Fireworks at "owner's representative" item - was
there ever a vote to authorize Chairman to procede with securing
staffing--and
if so, who from the Committee/Town/etc. should review responses to
advertisement.
As an interested citizen, "About Town" might want to know some of these
answers--and wonder why so many communications take place via
e-mail???
Are these communications open for public inspection???
School
Building Committee, Wednesday, May 22, 2002, Town Hall Commission Room,
7:30pm
Agenda
1. Report
on contract with Brooks Laboratory for East and South House window
projects/to
be moved along
2. Bisceglie
Park Project Update/nothing new--State DEP still considering status of
septic fields at Park
3. Order
of Magnitude Budget Review for entire school project/at this point,
expectation
of "overrun" might be more than $8 million without revisions--Committee
wants to bring the costs back to Town Meeting approved amounts.
"About
Town" will not publish more detailed reports until the School Building
Committee has had time to digest this information--in fact,
Fletcher-Thompson
wants an extra week to work on their own estimate of costs before we
get
into June cycle of "Design Development." There will be a short
School
Building Committee meeting next week to approve immediate projects with
proper contract procedures related to the School Construction effort.
School Building
Committee and Design Workshop, Wednesday, May 15, 2002, 7:30pm, Town
Hall
Commission Room
AGENDA
Approval of
Minutes/done, Ejector Pump (WMS)/OK, Bisceglie Park Update/given, South
and East House window projects/moving ahead, Invoices (to pay for
consultants
on traffic, etc., plus Fletcher-Thompson work in schematic design)/OK,
Discussion of May 8, 2002 Master Plan Project Schedule/some things are
behind, some things are probably over budget--will know better next
week-DRAFT
booklet several inches thick presented to members of the School
Building
Committee); DESIGN WORKSHOP on 3-4-5 School.
School Building
Committee and Design
Workshop,
Wednesday, May 8 at 7:30pm, Town Hall Meeting Room
"Weston Sports
Complex" architect and leader present option for lighted field (s) to
School
Building Committee--which is not enthused with the lighting concept,
but
does work with "Complex" architect to explain how the site plan has
changed
in recent weeks. The large area for paved parking and the large
area
footprint for new "Booster Barn" shown in not-to-scale drawing may
change
after the School Building Committee showed their revised site plan to
the
"Complex" reps. This meeting lasted until @10:20pm, with perhaps
the last hour devoted to the WHS plans and neighbors of the "Complex"
explaining
to the Building Committee what they would live with and what was
unacceptable.
School Building
Committee and Design Workshp, Wednesday, May 1 at 7:30pm, Town Hall
Meeting
Room
AGENDA
Review of
Outstanding Invoices
Bisceglie
Park Report/presented brielfly--discussion of how the timetable for
construction
hangs on Bisceglie projects.
South House
Roof Report/nothing new
Design Workshop
- 3-4-5 School and School Campus Site Plan
School Building
Committee, Wednesday, April 24, 2002, 7:30pm, Town Hall Commission Room
AGENDA:
Approval of
minutes; done, with quorum present.
South House
Roof project update; will be done with Building Committee
supervision
Bisceglie
Park project update; May 1 opening of discussion at Conservation
Commission; emphasis on oversight and management of projects
given
by School Building Committee Chair; Parks and Recreation points
out
that its bonding amount should not be spent on items not part of
Morehouse
Farm Park development or Bisceglie Park fields. This part of the
meeting
ended at 8:35pm.
Design Workshop
Middle School
Auditorium and additions
3-4-5 School--this
item deleted and replaced by discussion of "campus site plan" 9am
Tuesday.
Meeting ended at 10:05pm.
Dessign Workshop/School
Building Committee, April 17...next meeting in one week...
So what is
the latest? O&G at work...Reese Hobin to be at next Building
Committee meeting (with indication of where we are $$); Design Workshop
on 17th at earlier hour--7pm; Special Parks & Recreation
Commission
Meeting April 22 at 7:30pm...
Committee
meeting weekly--things picking up...Hurlbutt Roof-related projects to
be
handled "in-house" with supervision by Building Inspector (May 17 is
'inspection'
for roof and facade)...
SEPTIC IMPROVEMENTS:
State of Connecticut
DEP will not allow us to go ahead with on-campus septic systems (on
Revson)--after
tertiary treatment on campus, all "clean" effluent to go to Bisceglie
septic
fields--to be constructed/designed under new baseball fields
there.
Approvals could come and work begin by the end of July.
For more about
"Design Workshop" on 3-4-5 and High School, click HERE.
Bisceglie
Park Plan to Conservation for "receipt" Wednesday, April 10, 7:30pm:
School Building
Committee April 10 (Wednesdays - at 7:30pm in the Weston Library) to
finalize
designs for High School
At
the School Building Committee on April 3, it was revealed that the
acquisition
of 16 Parade Ground Court was going to happen; MEETING, MARCH 21,
2002, TOWN HALL COMMISSION ROOM...COINCIDED WITH BOARD OF SELECTMEN'S
MEETING--CONSTRUCTION
MANAGER SELECTED BY SCHOOL BUILDING COMMITTEE...confirmed at April 4
Selectmen's
meeting...
PRIOR TO DESIGN
WORKSHOP AT 7:30PM (IN COMMISSION ROOM) EXECUTIVE SESSION TUESDAY, Feb.
27, 7pm to 7:30pm - "Contract Negotiations" (for Construction
Manager???
or for something else???).
From what
we could see through the windows of the Commission Room, Construction
Management
firms were being interviewed by the School Building Committee (in
executive
session) Wednesday evening, Feb. 20...
School Building
Committee Wednesday, February 20, 2002 7pm Executive Session with, it is
reported now, the Board of Selectmen; 7:30pm Construction Manager
Interviews, Town Hall Commission Room...does the public have a right to
know about more than they are being told? Frankly, it is better
not
to know sometimes...then the only people who can be blamed for mistakes
made later are the people who made sure that no one else knew what was
going on in the first place!
School Building
Committee Tuesday, February 19, 2002, 7:30pm-10pm, Town Hall Meeting
Room:
in attendance - Wolf, Steube, Cunningham, Fitzpatrick; Gary,
Uzenoff,
Swerlowe; Engineer John Conte, Architrct Joe Costa (F-T),
Uzenoff,
Juneau (P&R); Town Administrator Tom Landry, Cynthia
Williams.
NOTE: actions taken at meetings where mistakes in procedure have
been made might be subject to procedural objections...and by the way,
is
the "School Building Committee" a different body from the "Building
Committee"
and is it necessary to have separate postings for these two
organizations?
AGENDA: Actually
a discussion not on the agenda (poorly explained on the official
notice)
of how the Town Engineer is dealing with pump problem at Middle
School;
bids reported on re: plumbing fixtures. Votes to be taken
at
meeting of the 20th--isn't it only in executive session??? Too
much
going on at once--but of course, "About Town" has been saying this long
enough to be mistaken for a broken record...and finally, the only item
on the agenda came up--discussion of "Project Scheduling." This meant
that
the Building Committee (not "school" building committee?) had to
schedule
its own projects--10 of them--to be supervised IN ADDITION TO BOND
ISSUE
SCHOOL PROJECTS by the same individuals. The attendance at this
meeting
was not good--only a bare quorum of the Building Committee (4).
There
were three (3) members of the School Building Committee in
attendance...these
are the ten (10) projects and assignments (first names only for
privacy):
- South House Windows
- Joe and Frank
- East House Windows
- Joe and Frank
- Septic Treatment
- Don and Mike
- Bisceglie Park
- Dave and Allen
- Morehouse Farm
Park - John and Doug
- Revson Field -
Don and Mike
- Hurlbutt - Allen
and Ellen
- Toilet Fixture
(campus) - Doug and Dave
- Ejector Pump -
Town Engineer
- Middle School
Roof and Floor Drains - Town Engineer
School Building
Committee,Feb. 13, Wednesday, 7:30pm Town Hall Commission Room; some
invoices
ok'd, consultants approved (this is what "soft costs"
means)...executive
session re: choice of construction manager.
Design Workshop
Feb 12 -HERE for reports on previous doings of this sub-committee...no
voting here...
School Building
Committee Feb. 6 in Executive Session to discuss contract...no
decisions
made here.
in
executive seeion--we will not thus being attending...
Special Building
Committee Meeting, Wednesday, Jan. 30, 2002, 7:30pm, Town Hall
Commission
Room
Tentative
AGENDA: four items, including East House window replacement
design
services (Fletcher-Thompson), traffic impact and access analysis
proposal
(Frederick P. Clark); constructionmanager proposals discussion;
any
other business (are they allowed to do this for a Special Meeting?)
School Building
Committee Design Workshop, Tuesday, Jan. 29, 2002, 7:30pm, Town Hall
Meeting
Room
Design workshop
with School Building Committee, Board of Education, and Parks and
Recreation,
and Fletcher-Thompson - great meeting: read about details of it
HERE.
Design Workshop
participants critique
Fletcher-Thompson, the process.
School Building
Committee, Wednesday, Jan. 16, 2002, 7:30-10pm, Commission Room of Town
Hall
Discussion on
number and length of meetings and workshops/7:30-10pm limits
Discussion on
Supplemental Survey Mapping School Campus/must have one A-2 for the
campus
Discussion/decision
on RFP for school bathroom fixtures/ready to be sent out
Discussion on
Middle School Proposal for pump and drainage: Fletcher-Thompson
Discussion on
proposal for fees for supplemental professional design service/East
House
Window Replacement, F-T
South House Window
replacement, F-T/now an environmental problem remediation case
Proposals for
geotechnical and ecological services, F-T/for going to Conservation and
the Army Corps
Building Committee
Design Workshop: Wednesday, Jan. 9, 2002, 7:30pm, Town Hall Commission
Room
For link to
Design Workshop page (official notice indicates that this is a
"preliminary"
design workshop).
SCHOOL BUILDING
COMMITTEE, WEDNESDAY, January 2, 2002, Weston Library, 7:30pm-10:50pm.
- Minutes of the
Dec. 5 and 19 meetings approved
- Approval of RFP
for Construction Manager - sent to Town Attorney
- Ed Specs for High
School O.K.'d
- Capital Plan Projects
discussion - timing of these with fixtures work at three schools
- Discussion of
RFP for School Fixtures. RFP for all schools in progress.
- Update by Don
Gary on septic - need to get a few months of use of low-flow fixtures
for
D.E.P.
- Update by Bob
Uzenoff on fields and parks - tennis courts back to School Road; all
fields
at Bisceglie w/o tennis.
- Any other business
that should properly come before the committee: Weston Sports
Complex
report, dated January 2, 2002 submitted by steering group: click HERE
for viewing sample sports complex (in Ridgefield), scanned from "Weston
Sports Complex 2003."
SCHOOL
BUILDING COMMITTEE, Wednesday, Dec. 19(Town Hall Commission Room,
7:30pm)
First Selectman
in attendance at School Building Committee...as well as Parks and
Recreation
Chair. and Town Administrator:
With almost
complete School Building Committee attendance, business done included
adding
an item to their agenda regarding changes to the Education
Specifications
by the Board of Education (reducing size of 3-4-5 by 2 rooms or 2,700
square
feet). The Chair. of the Board of Education made this
presentation,
noting that on the advice of a demographics consultant, the Board
decided
to make the above recommendation. In action based on the Dec. 13,
2001 letter from the Board of Education to this effect, the School
Building
Committee unanimously affirmed committment to this new Ed. Spec. - let
schematic design to begin soon!
An RFP for
Construction Management for the school projects was presented by the
School
Building Committee member assigned this task, and it was approved for
use
in soliciting submissions by (O&G and Turner). The problem of
shifting personnel in a long-term (4 years) effort was discussed.
East House
final invoice was approved-with-holding $400 until evidence of growing
grass was clearly visible.
A Sports Complex,
funded up to $2.4 million by contributions (not yet garnered) was
proposed
by a citizen. This would provide an artificial football field to
go with the artificial track--and be ready sooner than the plan
approved
by the voters at Referendum. A new Booster Barn and soccer field
may be able to be included. The Building Committee gave its
unanimous
approval to the idea of forwarding the process so long as the main goal
of school, septic construction would not be interfered with. This
meeting ended with the commitment of the Regular Building Committee
(which
meets twice a month--next on January 9) to meet on the alternated
Wednesday
evenings for "Design
Workshops"
to make sure Weston gets the best architectural solution possible
within
budget. The meeting adjourned at 10:30pm approx.
SCHOOL
BUILDING COMMITTEE "Contract Sub-Committee Meeting"
Monday, December
17, 2001
7:30pm Town
Clerk's Office
CONTRACT NEGOTIATIONS
(IN EXECUTIVE SESSION)
SCHOOL
BUILDING COMMITTEE MEETING, DEC. 5:
With more
than a quorum present, the School Building Committee conducted a 2 and
1/2 hour meeting (7:30-10pm, approx.). A member was designated to
represent the Building Committee at a Dec. 13 meeting with the First
Selectman
and the Jarvis Military Academy Committee. Next, minutes of
November
19, 2001 meeting were approved.
Discussion
with the Board of Education Executive Committee took place. The
"Ed
Specs" are being revised by the Board of Education to reflect Dr.
Prowda's
lowering of projected maximum student population eight years out.
Specifically, the new 3-4-5 school is anticipated now to be topping out
at 669 in 2008, rather than 750. The Chair. of the School
Building
Committee needs the numbers in December so that work on design, etc.
can
begin--to keep to the schedule. It was remarked that time lost in
the beginning of projects, or the converse, loomed most significant as
work progressed later on.
Discussion
with Don Gary, Septic Committee Chair., then took place. The new
news is that DEP has not officially given its OK to septic fields and
their
capacity at Revson. Conservative planning would thus require
septic
fields at Bisceglie be developed and connected to the School Road
facilities.
Conservation measures, low flow devices and design of a tertiary
treatment
plant (behind the Middle School, near the Town Garage) are next on the
docket for the Select Committee...
Discussion
with Robert Uzenoff, Parks and Recreation Commission and staff revealed
that coordination in some of the approved projects from Referendum will
be required to get the whole school upgrade underway (in the opinion of
this WEBsite). Playingfields for school activities, including
tennis
courts replacing the Town Courts next to the existing football field,
would
be provided at Bisceglie--if that part of the whole plan is begun early
enough...coordination of site work, to save money, would be
advantageous,
as well.
Discussion
RFP for Construction Manager as well as note to discuss the charge
and mission of the design subcommittee
will take place at a future
meeting. The Building Committee/School Building Committee meets
the
first and third Wednesday of the month (the first in the Weston Library
Community Room, the third in the Town Hall Commission Room). We
did
not pick up which room the Design Subcommittee would use on the second
and fourth. Special Meetings are posted and located as required.
REFERENDUM
PASSED NOVEMBER 15, 2001 - Full speed ahead on doing the $79+ million
will
of the majority...
EVEN OLDER
"ABOUT TOWN" MEETING NOTES FROM BUILDING COMMITTEE/SCHOOL BUILDING
COMMITTEE...CLICK
HERE FOR MOST RECENT NOTES.
SPECIAL
BUILDING COMMITTEE MEETING OCT. 25
Present:
Dave Coprio, John Cunningham, Ellen Uzenoff, Richard Wolf, Michael
Greenberg
The meeting
began at 7:34pm in the Commission Room at Town Hall. In reviewing
the text of the draft flyer to be sent out to all households, members
of
the Building Committee felt that more could be said in support of the
proposal
for $80 million dollar bond issue. As noted by members of the
School
Building Committee, at "coffees" around town (at least one referred to
specifically) attended by members of the Board of Education and the
recently
discontinued "Select Team" for school planning, attendance has been
slight,
but generally misinformed until the "coffee" presentation. For
possibly
approving a rewriting of the flyer, it was suggested that another
meeting
on Monday next (must be posted by Friday at 4:30pm) be held.
NOTE:
This last event may or may not take place (only this observer's
impression).
Adjourned at approximately 8:30pm plus or minus a few minutes.
Building Committee
Agenda, October 17, 2001:
Town Hall
Commission Room, 7:30pm
AGENDA
1. Discussion
of close-out work on Septic Fields/tabled
2.
"
"
"
" " East House Roof/discussed
3.
"
" time-frame and procedure to south House Roof Project/discussed
4.
"
"
"
"
"
for replacement of South House windows/discussed
5. Any
other business...discussion of approval of text for referendum.
At the Board
of Finance on Thursday, October 11...
Building Committee
Chair. supports First Selectman and proposals while reminding assembled
multitude that more work than is included in the 3 resolutions proposed
to the Board of Finance, now to go to Town Meeting and Referendum, must
be done (in his Committee's professional opinion) to Hurlbutt. No
one was listening--or wanted to hear it.
School Building
Committee, September 19, 2001
At this brief
meeting, a bill was approved and another proposal on roof design was
tabled.
Special School
Building Committee meeting on Wednesday, August 15...waiting for final
word that will eliminate off-site building location (preK-2 at
Bisceglie).
NOTE: first surveyor attacked by yellow jackets in the midst of
taking
measurements at Bisceglie--job awarded to second surveyor.
Results of second survey not available until August 28 Select Team
meeting.
NOTE: not ready then, either. Otherwise, School Building
Committee
endorsed latest revisions plus relocated School Road (one "no" vote on
this part of the program). There will be an early meeting prior
to
the Special Selectmen's Meeting Tuesday, August 21
(in Town Hall at 7:30pm--we think this is the right time, etc.).
REVISION #9
discussed at Select Team--to be voted upon, perhaps, by School Building
Committee Wednesday, August 15, 2001 at its 7:30pm meeting in Town Hall
Commission Room. Bisceglie option for preK-2 may be laid to rest
as well as definition of final budget figure for whole project...or
maybe
not.
Board of Finance
(August 9) OK's funds to continue consultant on school plan (for
preparation
for next Town Meeting) - up to $45,000...discussion of timeline made
with
expected vote between Election Day and Thanksgiving. Big meeting
coming up August 21 (at Board of Selectmen) with decision having to be
made by September 1 in order to meet above end date for vote on school
project.
Informal School
Building Committee meeting July 25 at 7:30pm:
Indications
are (to this WEBpage, at least) that a 3-4-5 school and renovations to
the high school (totally @$60million) will be what we end up
with...wasn't
that what O,R&L suggested?
AFTERMATH
OF ADJOURNED TOWN MEETING MACHINE VOTE:
What happens
now that Item #4 was defeated at Machine Vote...what will the Board of
Selectmen do to keep the architect working over the summer...design
sub-committee
of the School Building Committee cancelled July 5th 7pm
meeting...School
Building Committee to meet Wednesday, July
11, 2001, 7:30pm in Weston Library.
No meetings
of this group since Adjourned Town Meeting said "NO" by 15 votes...
Special Meeting
of Sub-Committee on Design, Monday, June 18, 2001 at 7:30pm in the
Commission
Room at Town Hall began early, and then had to move to the Meeting Room
(Planning and Zoning Commission had reserved it for its regular meeting
at the beginning of the year). Fletcher-Thompson team represented
by five staff members plus landscape design/traffic planner (we think
that
is who he was)--this a really big project, with two major buildings
involved
(new 3-4-5 school plus High School renovations). Discussion of:
massing and
location
of new building (3-4-5),
circulation within
Weston High School,
consultants on
civil engineering and traffic planning,
Ed Specs dated
May 7 - "About Town" to attempt to get a copy of these - and how to
best
meet these standards while still making consistent architectural
statement.
Road location
and possible need to have emphasis on circulation within the superblock
of School Road Complex.
Four members of
School Building Committee present plus another architect who lives in
Town.
"About Town" attended from @7:15pm to 9:30pm.
School Building
Committee gets OK from Selectmen...
Special Building
Committee Meeting, Monday, June 11, 2001 at 7:30pm in Weston Library
"stacks"
recommends moving forward this summer on "sketch planning" for 3-4-5
school
and renovations to Weston High School ($754,600 to the architect)...to
go to Special Town Meeting June 21, 2001 at 8pm in W.H.S. Auditorium
Special Building
Committee Meeting,Tuesday, June 5, 2001
AGENDA
1. Review
Fletcher-Thompson's fee and contract proposal for the designing of a
new
grades 3,4,5 school/no report from F-T or representative to Select Team
recommending an option
2. Review
Select Team's recommendation for school expansion project/see above
3. Review
contract for East House Roof/done partially
4. Review
South House window bid documents/done
5. Review
of replacement fields for South House and East House septic fields/more
work explaining this needed.
Building Committee Meeting on May 9, 2001 at 7:30pm
lasted
until 10:30pm - this meeting had been posted as well by the Select
Team...Board
of Education also co-sponsoring; standing room only;
architects/construction
managers presented costs for Scenario #1b and Scenario#3 and noted ALL
the possible alternatives to these and possible areas to cut had backup
but would not be presented at this meeting unless requested.
SCHOOL BUILDING COMMITTEE, 4-11-01
Sequestered
in the stacks of Weston Library, the School Building Committee members
heard from O&G/AP, the construction managers, that the cost of the
alternatives being considered would be...bigger than a breadbox (no
numbers
being allowed to be mentioned before they are REALLY sure...presumably
so that the Board of Selectmen, who will make the decision about which
alternative flies, will not be sandbagged). Also, no one wants to
say the number until analysis can be done that revises some aspected of
the plan to a workable figure).
SCHOOL BUILDING
COMMITTEE SELECTED CONSTRUCTION MANAGER ON 4-1 VOTE...Board of
Selectmen
4-5-01 at Special Meeting approves contract and meet construction
managers
from O&G and AP.
How about
the comment at Wednesday's Select Team meeting, from Fletcher-Thompson,
that the footprint for the 3-4-5 school shown on O,R&L Plan was not
the right size for a school building of this type! This puts the
first choice site for a 3-4-5 by the Building Committee in doubt...is
this
correct? If so, why didn't any other Board or the Building
Committee
itself notice?
THE FOUR ALTERNATIVES:
Click HERE for
Fletcher-Thompson four alternatives..."outline" only...
Feb. 21 meeting
of Building Committee produced sheaf of papers, a copy of which is
available
at the Town ClerK's Office. "About Town" attended the meeting and
received all documents. NOTE: among the six separate memoranda is
a major document "Various Scenarios-Proposed Matrix."
Fletcher-Thompson
speaks at community meeting on Saturday, March 3--no drawings yet, but
indications given that: the size of the "Field House" in previous
plan twice as large as other neighboring communities' (if lockers are
revamped
at the existing building) and two story addition above existing
classrooms
not workable. NOTE: Tai Soo Kim had suggested addition at
W.H.S.
at front of building (rather than a second story), expressing design
considerations
for distinct use of space as new unit (maybe air-conditioned--my
idea).
FOR THE RECORD: Building Committee
interviewed
architects and made choice (Fletcher-Thompson; Jim Beaudin) to
recommend
to Board of Selectmen; all three firms were excellent, and the
members
of the Building Committee were appreciative of their patience and
cooperation
in this convoluted process.
About Weston
skips Selectmen's discussion of insurance policies, attends instead...
BOARD OF EDUCATION
SPECIAL MEETING JUNE 22, 2000:
What was particularly
interesting about this Special Board of Education meeting called to
deal
with "Handling Enrollment Growth" was the emergence of pre-school
parents
(very angry at the Board of Education) who were concerned about the
possible
loss of their entitlement of modified full day kindergarten. They and
others
spoke during "Public Comment." Points made were:
Select
Committee should not be given more than 90 days to come up with
sewage
disposal alternative
No one will be
happy with the outcome
Three speakers
pro-new high school
One "forget about
it"
Year-round school
with air-conditioning and siblings "tracked" to assure that vacation
schedules
meld; re-negotiate teachers contract; field house with underground
parking
garage (this person said he has 10 month old and 6 year old)
1/2 day kindergarten
OK as interim--but remember Claire Gold's report! Also, the "new
high school" is actually what O,R&L proposed making out of the old
high school; put what is going to pass on the ballot
Consider kindergarten
at churches; use Library Community Room for art/music; St.
Francis parking lot a good site for portables? Re-negotiate
teachers
contract--maybe teachers could have lunch in their classroom with their
class? Be more creative.
When will 2000-2001
decision re: kindergarten be made? (No answer--this was discussed
later)
Portables for
kindergarteners not good
select lesser
of evils (i.e. long enough day as opposed to 1/2 day just to stay on
campus[?])
Breezing through
the agenda, "Dr. T" (Dr. Len Tomassello, Hurlbutt) then addressed the
Board
regarding solutions he and his team had found. In summary:
The assumptions
made were that modified full day was still the best--cited Claire Gold
report re: early intervention. Link here to conclusions of the
report:Conclusions
printed here.
DR.
T'S TEAM'S ASSUMPTIONS:
- there will not
be more than this year's 5 new portables (in place at the Weston Middle
School) allowed
- current level
of service for all grades
- IF level of service
to children must be curtailed, THEN only 4th grade would be exempt.
PERSONNEL:
Kindergarten teachers must not be forced to teach two sections of 24
children
each in the same day
FACILITIES:
East House for Kindergarten and first grade only; South and North
House should mix grades 1-2-3- and 4. NOTE: if the
Westport-Weston
Health District could be prevailed upon to permit more portables on the
Hurlbutt site, a place for 5 more portables between the Library/North
House
and East House and/or South House would make life easier for the school
children...because without more new space in 2001-2002 school year
alternative
OPTIONS will have to be considered.
OPTIONS MUSIC:
- Talent on Tap
impacted if music room taken--music in South House Cafeteria (the
cafeteria
situation is very serious; many comments)
- reduce music to
lower grade(s) to serve 4th grade; concerts affected
- maybe use East
House cafeteria for music
OPTIONS ART:
- art on a cart--reduce
level of art service because of lack of adequate space
PHYSICAL EDUCATION
(P.E.):
- not enough space
- classes double
booked in South House cafeteria
COMPUTER LAB:
- reduce k-3 computer
use--no computer for k
- satelite stations
for music
- computers moved
to classrooms
LIBRARY:
- flexible access
to library eliminated (because of 46 minute period for 4th grade)
QUESTIONS FROM
THE BOARD:
- can we go back
to WWHD to get more portables? (no answer)
- we are at a
crossroads
(self-evident)
- educators want
to move ahead with improving education (good luck)
- what do we do
next year? (same drill as this year)
- will we look
off-campus
for kindergarten solution? (already on it)
- modular construction
k-2 at Heady site?
- is it reasonable
to assume that Heady can be used?
- could we place
a lot more pressure on other Boards?
- we should have
had contingency plans (in retrospect)...hard choices
Departing school
board member remarked that political decisions are made in
crisis...there
are no new ideas...Board of Education has no power to make its plans
come
to fruition because it never considers the cost of anything...no one
wants
to share a high school...the best thing that has happened recently is
hiring
Dr. Shaner, who will lead. Financial decisions and the septic
problems
will over-shadow others.
Meeting ran
from 7:45pm to 9:30pm.
NEXT BOARD
OF EDUCATION MEETING JULY 17 at 7:30pm.
CTDEP SPEAKS...
The other
shoe drops...found on the Weston Board of Education WEBpage is
commentary
from the Superintendent indicating that via a telephone call the day
after
the May 25 PUBLIC HEARING, the CTDEP representative is quoted as having
said "...things 'aren't that drastic yet'" regarding limiting the
number
of students at Hurlbutt. CTDEP goes on to say that we need to
decide
by September a temporary solution to the septic issue (i.e. pump and
haul).
"About Town" would like to know whether the CTDEP indicated which
September
they were planning to act...
1. Master
Schedule changed...Selectmen appointed Ad Hoc "Select Committee" for 90
day+ stint to come up with new ideas, using data collected by
Fuss&O'Neill
as well as other Town studies, thus reworking plans for Septic/Sewer
already
presented; Planning and Zoning, Conservation, Board of Education
and Building Committee plus five citizens were named June 15...worked
during
summer vacation...link here to information about progress and
re-appointment
of Select Committee: SEWAGE
TREATMENT COMMITTEE.
2.THE FINAL
SCHOOL FACILITIES PLAN (now on hold) TEXT AND DETAILS...
3. FROM ULTIMATELY
SELECTED OPTION OF CJN ASSOCIATES' MAP OF 100+ ACRE CAMPUS
FOUND HERE!
Building Committee
June 8, 2000 at 7:30 in Town Hall:
Five members
of the Building Committee (two others absent) plus two members
additional
making up the School Building Committee (Superintendent of Schools and
member of the Board of Education) met to discuss trips upcoming to
architects'
(Jeter, Cook and Jepsen; Tai Soo Kim and Fletcher-Thompson) offices and
school buildings they had designed.
Another item
on the agenda was a discussion of sewer/septic issue and the Building
Committee's
role in the future on this topic. The Chair. was appointed to sit
on the new "Select Committee…" that will be studying sewer options over
the next 90 days. A spirited discussion took place about what the
impact of a tiny sewer line to just the Schools and Town Hall would
be--and
if indeed the implications for development density would be almost nil,
as some members of the Building Committee purported. Members of
the
Building Committee believe that "a tiny sewer line bringing only
60,000+
gallons of effluent from Weston to the Norwalk treatment plant" (as
described
in Fuss&O'Neill report) thus setting a limit on development) would
permit Weston to then say no to affordable housing applications along
the
route of the sewer.
Members of
the public were invited to participate in this meeting, and it was also
discussed whether inviting AVALON, affordable housing construction
company,
to propose an example of how an affordable housing scheme might work
for
Weston would be a good idea.
Selectmen
OK $765,000 for architects' conceptual drawings; school
construction
projects still alive...architect interviews continuing? It is a
puzzlement,
but we are apparently interviewing architects if and when we figure out
what we want/need/can actually follow through with...
SELECT
COMMITTEE ON SEWAGE TREATMENT now appointed and first meeting took
place Monday, June 19, 2000 at 7:30pm in Town Hall; tent. next
two
meetings: June 28 and July 6., 7:30pm in Town Hall...
SCHOOL BUILDING
COMMITTEE INTERVIEWS, MAY 8 and 9, 2000,TOWN HALL MEETING ROOM
Town Hall Meeting
Room, May 8, 2000, 7pm to 9:45pm; May 9, 2000 report from
indirect
sources; NOTE: as of June 14, 2000, this process is rolling
along,
with final three firms being visited plus site visits to examples of
their
work.
NOTE:
it is the intention of the Building Committee to check out references
and
projects by these architects; they may invite firms back for more
questions; need to visit examples of work and offices.
Selectmen
OK ED SPECS FOR State Funding by June 30
Board of Selectmen
(May 4 meeting) approved extra payment ($19,200) for School Planner to
draw up education specifications...Ed Specs for four part Plan.
Four
buildings and areas around them will be separate applications.
For
example: the new 3-4-5 building and attendent fill, paving,
fields
is one; the high school project plus moving School Road is
two;
the Middle School auditorium and renovations plus loop road is
three;
Hurlbutt renovations and School Road entrance is four. So easy to
explain! (These are my guesses--not confirmed what the four separate
projects
will actually be.)
MAY 18 and
May 25 Dates to note...
On May 18,
2000 at 7:30pm in the Weston Library Fuss&O'Neill will present
their
draft plan for sewers/septic to Town of Weston Boards and
Commissions.
The public is invited...but not to speak. On May 25, 2000 at 8pm
in the W.H.S. auditorium, there will be a PUBLIC HEARING on this same
proposal.
On June 1, 2000 (est.) at the Board of Selectmen, a decision will be
made
by that Board, and a recommendation will be made to the Board of
Finance
and then to Town Meeting...more dates for more meetings to come...see
above.
RESPONSES
RECEIVED OFFICIALLY TO RFP Monday, April 24 at 11am in Town Hall; only
the name and address revealed at this time.
Nine (9) architectural
firms repond to RFP and five make it through successfully. Making
it to the next level are the architectural firms in red and
underlined--the
first "cut" by Building Committee was:
1. Wiles
and Associates (Bridgeport)
2. Fletcher-Thompson
(Bridgeport-now in Shelton) - ARCHITECT NUMBER FOUR (current)
3. DiCarlo
& Dahl (Hamden) - ARCHITECT NUMBER ONE - responsible for 4 room
addition
at North House (with foundation for 4 more rooms)
4. Schoenhardt
Associates (Simsbury)
5. Friar
Associates ARCHITECT NUMBER TWO (Farmington) - they designed and built
the Hurlbutt Core Building and enclosed linkages in their first phase,
as well as modifying rooms at WMS, building a new DPW Garage on Old
Hyde
Road and Board of Education Headquarters on School Road.
6. CJNA
- Charles J. Nafie & Associates - (New York City) - ARCHITECT
NUMBER
THREE (did Master Plan, prepared SFU documents)
7. C.J.
Lawlor (West Hartford)
8. Tai Soo
Kim (Hartford)
9. Jeter,
Cook and Jepson (Hartford)
On Tuesday,
after the Building Committee had met, "About Town" looked through all
nine
responses to the RFP...all references to price/cost were removed (so
that
this matter can remain confidential and be negotiated).
SCHEDULE
THROUGH EARLY 2003 NOW HISTORY...new goals and milestones reported on
at
June 11, 2003 meeting. See below the schedule for bids released at
School Building Committee meeting (by O&G) Oct. 1, 2003:
Weston Field Committees thru the years...


BOOSTER BARN AS ORIGINALLY SHOWN NEVER BUILT - NEW GROUP
FORMED, TOWN TAKES CHARGE - NEW BOOSTER BUILT.
- LATEST
INCARNATION WINS OK FROM BOARDS OF SELECTMEN AND FINANCE!
ARCHITECT KAESTLE-BOOS/BLDG COMMITTEE ON THE JOB...TO PAY BACK TOWN $$
OVER TIME
- Presentation
by original Sports Complex team re:
discussing fitting into entire
workplan;
- This is really happening in a terrific
way--all weather field complete
and ready for play by mid-October '03!!! (All-weather Hartford football
field above - Courant photo.)
- At the Board of
Selectmen July 20, 2006 came word of need to contribute another $4,100
toward completing the lighting of the Varsity Soccer Field on School
Road.
- At the Board of Selectmen in April 3,
2008, discussion of latest problems at Revson Field.
- If artificial turf is bad, Revson
grass mixes with glass - the only safe place to play is...in the
streets?
A Push To Know Whether “Crumbs” In Artificial Turf Can Make People Sick
Toxins In Artificial Turf Prompt Concern
By REGINE LABOSSIERE | Courant Staff Writer
April 12, 2008
As the use of artificial turf has increased in popularity, there is
growing concern that a component in some turf might be hazardous to the
health of people and the environment.
Several studies in Europe and a few in North America have shown that
rubber "crumbs" used in some artificial turf release toxins that might
cause health problems and might be poisonous to plants.
Although there is no scientific evidence that people are getting sick
directly because of their use of artificial turf, measures are being
taken to protect citizens...
Legislature
joins turf war on artificial
fields
Stamford ADVOCATE
By Donna Porstner
Published March 7 2008
STAMFORD - State lawmakers may commission a study on artificial turf
fields because of mounting concerns about possible health risks.
The legislature's Environment Committee approved a bill 24-5 last week
that would give $250,000 to the state Department of Environment
Protection to research whether materials in the pulverized rubber tires
used to cushion the fields are harmful to users' health.
The sponsor, state Rep. Kim Fawcett, D-Fairfield, said she had thought
it was a great idea to use recycled rubber tires on playgrounds and in
artificial grass playing fields "until I learned what's in them."
Turf wars have heated up all over lower Fairfield County since a
nonprofit group's study last year found that when heated in a lab, the
rubber crumbs released at least four compounds - including one known
carcinogen - that can irritate the eyes and skin. Other studies have
shown tire rubber contains heavy metals that can leach into groundwater...
Previous
notes - over time, individuals changed but project continues...
SHINING A
LIGHT ON SPORTS COMPLEX PROGRESS:
May 2004 sees
the lighting issue for now completed high school artificial field at
Conservation...
The word (November
2002) on where the Sports Complex stands: although still shy of
the
original total $$ needed, there is enough money to proceed forthwith to
detail how exactly the all-weather soccer field will fit into drainage
on School Road, and coordinate with School Construction project as a
whole.
This will be accomplished for @$17,000 by school project's
environmental-landscape
design professionals. Architect for school project will design
new
"Booster Barn" gratis. Cognizant of potential for major disasters,
first
will be a full engineering review of plans for where each building
actually
is placed on the property, however...it is becoming clearer every day
that
2003-2005 will not be optimum time for athletic activity on the School
Campus. And it is a good bet that fields will not be ready at
either
Morehouse Farm Park or Bisceglie in a timely fashion, due to litigation!
Following
up on front page article in the FORUM...some early words about SPORTS
COMPLEX:
At the Wednesday,
January 2, 2002 School Building Committee meeting, a brief presentation
was made by W.H.S. Athletic Director, community Sports Complex 2003
steering
group...
Vision Statement:
"Support the
athletic energy of Weston's youth by providing leadership in upgrading
and enhancing athletic facilities which benefit all participants."
Mission Statement:
"Create, and
sustain, a 'Best in Class' Multi-functional athletic
environment/facilities"
is the idea! "...Weston High School's medium longer term total
land
use, athletic infrastructure and development strategies" are on the
line
here. Through mutual partnerships (individuals, families, public
enterprises), the Committee states, "...we will focus our development
efforts
towards providing a multi-sports surfaced stadium and supporting
equipment
to enhance overall athletic excellence."
This has been
done successfully "across the pond"... in Lancashire...JOINT
DEVELOPMENT
is one way to go in times of limited resources...
RIDGEFIELD,
CT IS THE MODEL FOR THIS PROJECT:
- The field surface must be
replaced,
- Fairly complex drainage structures and underdrain systems kept up,
- And
ponding would only take place on the field after more than two inches
of
rain had fallen (in an hour?).