

THE BRIDGE TO NOWHERE, SO
FAR...THAT'S WHY WE CALL THESE THINGS "DISASTERS"
Weston's
Cartbridge update: Bridge span to be laid next
week
Weston FORUM
Written by Kimberly Donnelly
Friday, September 19, 2008
After almost two and one-half months of delays early on, and a few
weeks later than predicted at the end of July, work on the Cartbridge
Road bridge replacement is expected to be done in just about a month
from now.
Tom Landry, town administrator, said everything seems to be
“progressing quite nicely” on the project, which is scheduled to be
completed by Oct. 24. There is a possibility the bridge will be open to
limited traffic about a week earlier than that, Mr. Landry said.
According to the latest revised schedule, four precast concrete bridge
span sections are supposed to be delivered and installed sometime
before Sept. 25, Mr. Landry said. Finishing touches then include
installing several layers of asphalt and striping the pavement.
Damaged
The bridge has been closed to traffic since it was damaged during a
storm in April 2007. Cartbridge Road, when the bridge is operational,
connects Goodhill Road with Lyons Plain Road.
Because President George W. Bush declared Connecticut a disaster after
the noreaster that damaged the bridge, the town was able to procure
partial funding for the bridge work from the Federal Emergency
Management Agency (FEMA) and get the project fast-tracked. FEMA is
paying for 75% of the estimated $1.269-million cost of replacing the
bridge. The town will pay the remaining $325,000.
Revised
schedule: Contractor says
Cartbridge Road bridge will likely open in
October
Weston FORUM
Written by Kimberly Donnelly
Thursday, August 07, 2008
A utility pole that stood in the way of progress on the Cartbridge Road
bridge replacement project has finally been removed.
The project, originally due to be completed July 2, now has an end date
of Oct. 27. But, it will likely be open to at least limited traffic
about a month before that.
Complete Construction Company, the contractor replacing the bridge over
the Saugatuck River, said in a letter to the town dated July 24 that
the replacement schedule has been “negatively impacted 80 working days.”
Reasons for the delay stated in the letter include “unrelocated utility
poles,” “higher than anticipated water levels,” and a “stop work order
for additional borings.”
Now that some of those obstacles have been overcome (including a
utility pole that had to be moved by Connecticut Light and Power after
electrical, telephone, and cable TV wires were moved), the contractor
has revised its construction schedule “to expedite completion of the
project,” the letter states.
The revised schedule calls for the four pre-cast concrete bridge span
sections to be delivered and installed between Sept. 3 and Sept. 5; it
will open Cartbridge Road to one-way traffic on Sept. 23; and the
project will be completed, except for the punchlist, on Oct. 2.
Tom Landry, town administrator, said he is glad to see some progress,
but he continues to monitor the project closely. “We’re pushing them
pretty hard” to get the bridge opened even earlier — “ASAP” — he said.
Damaged
The bridge has been closed to traffic since it was damaged during a
storm in April 2007. Cartbridge Road, when the bridge is operational,
connects Goodhill Road with Lyons Plain Road.
Because President George W. Bush declared Connecticut a disaster after
the nor’easter that damaged the bridge, the town was able to procure
partial funding for the bridge work from the Federal Emergency
Management Agency (FEMA) and get the project fast-tracked. FEMA is
paying for 75% of the estimated $1.269-million cost of replacing the
bridge. The town will pay the remaining $325,000.
First Selectman Woody Bliss said even with the delays, he is pleased
with the speed at which the bridge is being put back into service.
“We’ll be done in 18 months,” he said. “...That’s about half the time
[the Department of Transportation] told us it would take originally.”
Mr. Bliss credits Congressman Christopher Shays (R-4th) with expediting
the project. “He brought in FEMA and has been very supportive,” Mr.
Bliss said.
Because the town opted to go with the FEMA reimbursement, rather than
the slightly higher (80%) state reimbursement, it was able to avoid
many permitting and procedural holdups.
“We gave up 5%, but we got the bridge a year and half sooner. I think
that’s good economics,” Mr. Bliss said.
He compared the progress to that of the Wells Hill bridge, which is in
Easton, but connects to Wells Hill Road in Weston. “My guess is [Wells
Hill] will take twice as long as it took us to do Cartbridge ...
roughly as long as the state DOT tells you it will take,” Mr. Bliss
said.
Next up
As soon as the Cartbridge project is completed, the town still faces
yet another bridge replacement project.
The Valley Forge Road bridge has been listed in “poor” condition. It
was due to be replaced beginning the summer of 2007.
The town had to put that project on hold when the Cartbridge bridge was
damaged. “We couldn’t have two bridges out of service at the same time.
That would have been crazy,” Mr. Bliss said.
Unfortunately, he added, the Valley Forge bridge can’t go out to bid
until the Cartbridge bridge is finished, Under state law, bids are only
good for 30 days, “so we have to wait until we can be in a position to
award a contract,” Mr. Bliss said.
The town likely will accept state aid for the Valley Forge bridge, Mr.
Bliss said. It means that the total time to replace the bridge, from
engineering work (that has already been done) through construction, is
expected to be about three years, not including the delay while
Cartbridge has been under construction.
“That’s how long it takes to build a bridge. It just takes time,” Mr.
Bliss said.
Building
a bridge: CL&P relocates
pole at Cartbridge
Weston FORUM
Written by Kimberly Donnelly
Wednesday, July 16, 2008
Connecticut Light and Power (CL&P) has moved electrical wires from
a utility pole that is standing in the way of construction work on the
out-of-commission Cartbridge Road bridge. But, as of earlier this week,
the pole remains. The reason is that cable television and
telephone wires are still attached to the old pole.
Tom Landry, Weston town administrator, said CL&P began moving its
wires on Monday, July 7. Mitch Gross, spokesman for CL&P,
confirmed on Thursday, July 10, that the power company had completed
its portion of the work — sort of.
“Our poles and wires have been relocated,” Mr. Gross said. “As soon as
we finished our portion of the work, AT&T and Cablevision were
notified right away.”
Electrical wires are always located at the top of utility poles. Mr.
Landry said once the cable lines (always closest to the ground) and the
telephone lines (in between power and cable) are transferred to the new
utility pole, CL&P will need to return to remove the old pole.
First Selectman Woody Bliss said this week he was relieved the power
lines had finally been moved, but he is still anxious for the project
to move along. He met with the project engineer, Arthur DiCesare,
and representatives from the contractor, Complete Construction, at the
site last Friday, July 11. “Their estimate was a Sept. 15 completion
date,” Mr. Bliss said.
With all the delays the project has experienced in the past year,
however, Mr. Bliss is not quite ready to write that date on his
calendar in permanent marker. “We’ll see what happens. I’m pressing the
hell out of them to just fix it and get it going again,” Mr. Bliss said.
The bridge, which crosses the Saugatuck River, has been closed to
traffic since it was damaged during a storm in April 2007. Cartbridge
Road, when the bridge is operational, connects Goodhill Road with Lyons
Plain Road.
Because President Bush declared Connecticut a disaster in the wake of
the nor’easter that damaged the bridge, the town was able to procure
partial funding for the bridge work from the Federal Emergency
Management Agency (FEMA) and get the project fast-tracked. FEMA is
paying for 75% of the estimated $1.269-million cost of replacing the
bridge. The town will pay the remaining $325,000.
Plagued by delays
Construction on the replacement bridge began at the beginning of March
of this year, and was scheduled to be completed by the end of June, but
delays ensued almost immediately.
Work on the east side of the river could proceed only so far because of
the utility pole that was in the middle of what is to be the new
bridge. The wires on that pole could not be moved until a new one was
installed; the new pole could not be installed until easements with
neighboring properties were worked out. That included the town signing
an indemnification agreement on behalf of one of the neighbors.
Once it looked like the easements were in place, Mr. Landry said,
CL&P then claimed it needed to receive “aerial rights” across the
Saugatuck because its power lines would be in a new location.
A date was set at the end of June to finally relocate the wires, but it
was further delayed when CL&P said it needed more time because it
had to get approval from Call Before You Dig, a clearinghouse that
provides a communications link between anyone excavating and public
utilities that may have underground lines.
Other reasons
The delays have not all been because of the errant utility pole,
however.
When the contractor was drilling for footings, it stopped about five
feet short of what had been specified in the bridge plans, claiming it
had reached bedrock. The engineer disagreed.
As is, the footings that were in place were able to hold nearly three
times the weight that is specified for the bridge. The problem lay in a
question of adequate “scour protection.”
All drilling stopped around Memorial Day. About a month later, a
compromise was reached when the engineer and Complete Construction
agreed to put in four additional pilings instead of going to the
original depth. Construction workers were at the site last week
and this week, installing the pilings.
Cartbridge:
Bridge work hits more
roadblocks
Weston FORUM
Written by Kimberly Donnelly
Wednesday, 11 June 2008 12:14
As they often say in New England, you can’t get there from
here.
The old maxim is certainly true for those who were used to
traveling on Cartbridge Road, normally a common cut-through between
Goodhill and Lyons Plain roads. And it looks as if it’s going to
continue to be true until at least the end of the summer.
“At this point, we’ll be lucky if we make it in time for the
school buses to start using it again in September,” said Tom Landry,
town administrator.
The Cartbridge bridge over the Saugatuck was permanently
damaged in a storm more than a year ago — in April 2007 — and has been
closed to traffic ever since.
Construction on the replacement bridge began at the beginning
of March, and was scheduled to be completed by the end of this month.
“Not going to happen,” Mr. Landry said last week.
There are two main issues holding up the work, Mr. Landry
said.
The first is a disagreement between the contractor, Complete
Construction, and the project engineer, Arthur DiCesare, about where
bedrock begins.
Mr. Landry said when the contractors were drilling for footings,
they stopped when they believed they reached bedrock — about five feet
short of where they had to be to comply with weight and scour
protection requirements.
The engineer said it was just rock, not bedrock, and that drilling
should continue. Complete Construction disagreed.
The town hired another firm, Dewberry, to do some test borings.
Dewberry recovered core samples at the site and determined the bedrock
indeed begins about five feet below where Complete Construction stopped
drilling.
However, the contractor still does not believe it is necessary to
continue drilling, Mr. Landry said. The footings are required to hold a
maximum of 85 tons; at the depth they are now, they would be able to
hold about 220 tons, nearly three times what is specified for the
bridge.
The problem, Mr. Landry explained, is that for proper “scour
protection” — to ensure that the movement of the river bottom doesn’t
chip away at the bridge footings — they must drill the additional five
feet.
“They’re going to have to figure out how to drill a different way, or
they might have to leave the coffer dams at the bottom of the river,”
Mr. Landry said. That, however, is a much more expensive proposition
for the contractor.
Drilling stopped around Memorial Day, and as of this week, had yet to
resume. “We will get this resolved. Eventually,” Mr. Landry said.
Power company
The second major impediment to the bridge work is that Connecticut
Light and Power (CL&P) has refused to move a utility pole that is
in the middle of what is supposed to be the new bridge. Until it is
moved, work on that side of the bridge (the Lyons Plain side) is at a
standstill.
“CL&P feels there are potential easement issues,” Mr. Landry said.
The good news is that CL&P does have easements for the property
onto which it needs to move the pole on the Lyons Plain side of the
river, as well as for the property on which a connected pole sits on
the opposite bank.
The problem is that in moving the one pole, the angle of the power
lines that cross the river and connect to the pole on the opposite bank
will change. CL&P claims it needs “aerial rights” once those lines
move, and those rights are not specifically stated in the current
easement agreements.
CL&P has asked the town to indemnify it against any potential
future problems. Mr. Landry said he does not feel it is necessary for
the town to do so.
“They’re already there,” he said of the power lines across the river.
CL&P says it does not want to be responsible for problems with the
lines, but if they are already there, Mr. Landry asked, what’s the
difference?
The issue is getting closer to a resolution, Mr. Landry said. Town
officials and CL&P representatives had a conference call on June 5,
and CL&P agreed to temporarily move the pole. But the company still
has to decide whether to run the lines up Riverbank Road and along
Cartbridge Road (on the Goodhill side of the river) or to keep them
going across the river. So the pole won’t be moved until June 27.
“We don’t really understand what the problem is, and we don’t really
care,” Mr. Landry said. “For goodness sake, move the darn pole. I’ve
got a bridge to build.”
The contract with Complete Construction said the bridge work had to be
done within 150 days of signing, which would be the end of this month.
“We’re definitely not going to hit that date,” Mr. Landry said, but
some of that is the power company’s doing, he added. “I think there’s
clearly some need for accommodation here,” he said.
Mr. Landry said it is likely the bridge will not be open until the end
of the summer. The contractor cannot submit plans for the bridge span,
which is built off site, until the current issues are resolved. From
the time the plans are submitted, it takes at least five weeks to build
the span, he said.
JOINT
PUBLIC HEARING
At
Selectmen's special meeting on October 4, 2007 at 6pm, Cartbridge two
versions shown - new bridge design (see virtual bridge design above) to
receive joint meeting review by Conservation and Planning and Zoning
later in the month. See notice below.

Cartbridge
Road bridge goes to public hearing
Weston FORUM
by PATRICIA GAY
Oct 19, 2007
The plan to replace the Cartbridge Road bridge will be reviewed at a
public hearing on Monday, Oct. 22, at 7 p.m. in the Meeting Room at
town hall.
The hearing will be conducted jointly by the Planning and Zoning
Commission and Conservation Commission.
P&Z will decide whether the bridge meets the standards of
Connecticut General Statute 8-24, and the Conservation Commission will
discuss floodplain management and the bridge’s impact on wetlands.
Under an 8-24 review, P&Z must decide if the replacement of the
bridge is a suitable and appropriate use of town property.
The bridge was heavily damage by flood rains in April and has been
closed to vehicular traffic since then.
The proposed replacement bridge will be 9 feet longer than the existing
bridge but would remain the same height, said Tom Landry, town
administrator. He said it would be made from pre-cast concrete.
CARTBRIDGE BRIDGE - TOWN TO SEEK F.E.M.A.
MONEY
by BRIAN GIOIELE
June 13,
2007
With a disaster declaration in hand, town officials are pushing for
federal funds to aid in the replacement of the Cartbridge Road bridge,
damaged during the April nor’easter that doused the state.
The Board of Selectmen last Thursday, June 7, voted to authorize First
Selectman Woody Bliss to make a grant application to the Federal
Emergency Management Agency (FEMA) seeking 75% of the cost to replace
the Cartbridge Road bridge, repairs of Godfrey Road West at Pent Road,
and other related expenses resulting from the mid-April rainstorm.
Town officials have had four separate meetings with FEMA officials in
recent weeks regarding the damage, after President Bush declared
Connecticut a disaster area because of the destruction caused by the
April 15 storm.
Mr. Bliss said he was pleased with the declaration, since it meant
Weston would get a share of emergency funds to replace the bridge,
which could cost between $600,000 and $800,000, according to estimates.
Officials say that FEMA will reimburse the town for police and public
works overtime expenses, the cost of the Jersey barriers they had to
place on the bridge, vehicle mileage for trucks and police cruisers
during the storm, debris removal costs, and even expenses for meals
workers ate while on the job.
Some seek quicker fix
But even this reimbursement opportunity has not stopped some
residents from seeking a quicker resolution to the bridge closure.
However, town officials say bypassing the FEMA route still poses
potential scheduling roadblocks.
“We could do it ourselves with FEMA aid,” said Mr. Bliss. “It would
reduce the time schedule, it would reduce the number of permits
required, but it doesn’t get a bridge built this summer.”
Mr. Bliss said that even without the additional permits required with
FEMA aid, the town would still need to have hydraulic tests performed
before there could be any bridge designs completed. The plans must then
go to the state Department of Environmental Protection (DEP) for review
and approval, a process that could take up to two years.
“I’ve talked to people at DEP, told them about our situation, and was
told the process could be done in two to three months, possibly,” said
the first selectman. “In the end, there would be a few less permits,
but it won’t save us much time.”
The main concern is the traffic troubles on secondary roads in the area
of the Cartbridge Road bridge closure. Nearby River Road is being used
as a cut-through, and there is also more traffic on Goodhill and Lyons
Plain roads, which authorities say are not used to this type of traffic
volume.
Police Chief John Troxell said that the Police Commission last week
approved a plan to place stop signs at Goodhill Road at River Road,
making that intersection a four-way stop. Chief Troxell added that the
department will increase its presence on River Road as well in an
attempt to slow the increasing traffic on the roadway.
BOARD OF SELECTMEN HOLD REQUIRED
INFORMATION SESSION FOR PUBLIC, MAY 17, 2007:
This was planned way in advance for the the Valley Forge Bridge only -
20-30% done with design now, plan is to reroute traffic during
construction, (beginning optimistically, April 2008). A
Selectman, we think, asked if under the State Bridge program there was
anything like an "emergency" to speed up Valley Forge project,
considering that Cartbridge was no longer usable. The answer from
Department of Transportation engineer in charge - "No."
Questions about Cartbridge Bridge kept popping up - it is to be
repaired under the umbrella of FEMA (Federal Government), according to
First Selectman and folks from Maguire (engineers) and confirmed by CT
DOT...however, the DOT individual pointed out that there is an
"emergency" factor in FEMA regs - this is a good thing. (Now that CT
received disaster declaration, at least for infrastructure like
Cartbridge.)
IMPACT:
What is the
traffic impact on the Davis Hill Bridge, as well as the Valley
Forge/Lyons
Plan/Kellogg Hill intersection going to be like? Has anyone run
the numbers (i.e. traffic consultanr or SWRPA, which studied this
intersection and made recommendations in the past)? Can't be
good...we'll check the accident history on
roads and at interestions near these two operating bridges from time to
time...RIVER ROAD is fourth bridge in Weston - First Selectman reminds
us that there is one at this spot!
First Selectmen Peppered With
Questions
Westport News (part of story relating to Weston)
Don Casciato
May 16, 2007
"...A query about a bridge in Weston, which will be out of commission
for between six and 12 months, produced some angst. The person
asking the question claimed that Bliss' earlier answer to the man's
wife seemed 'specious' and he wanted to know why a temporary bridge
couldn't be installed...
"Another topic included flooding problems and how to cope when 'we
don't have the manpower. That's what keeps me awake at night'
said Bliss."
"On the...issue of affordable workforce housing,
Bliss said Weston lacks the sewers needed for such a project. 'The fact
of the matter is the bridge is in a federal flood plain'" said
Bliss. 'We are moving rapidly on our end...'"
Earlier report:
Cartbridge bridge replacement:
A long road lies ahead
FORUM
by PATRICIA GAY
May 9, 2007
The bridge on Cartbridge Road, which was severely damaged in the
recent nor’easter, is not going to be reopened anytime soon. “It may be
out of service for a year or more,” said First Selectman Woody
Bliss. According to Mr. Bliss, a report from a
team of engineers —
including a diver who explored the bridge’s underpinnings — states the
bridge cannot be repaired and must be replaced...full story here...