VIEW FINAL SCHOOL PLAN ON-LINE
Building Committee interviewed architects and made choice (Fletcher-Thompson) to recommend to Board of Selectmen;  all three firms were excellent, and the members of the Building Committee were appreciative for their patience and cooperation.


Agenda had been modified several times...Interviews took place and a discussion/decision was made Wednesday, Jan. 17, 2001 in the Commission Room at Town Hall at a three-hour meeting, beginning at 7pm.  Only the seven members of the Building Committee voted ("School Building Committee" includes Superintendent and member from the Board of Education).  NOTE#1:  the successful firm claimed success in "selling" more than one project at a time, and thought opening "the doors to the school" date of September 2003 was "do-able" in 20 months of construction.  This firm will look at all alternatives simultaneously.  NOTE#2:  Presumably, the Board of Selectmen will have to authorize any contract to retain an architect...
As "About Town" sees it, the FINAL SCHOOL PLAN noted above is to be modified as needed in order to meet a September 2003 deadline to "turn the key" on a new building of some sort. 
Most recently...

The New Committee is called The Select Team...formed Jan. 4, 2001--first meeting of this newest ad hoc committee will be in the WMS Library...it conflicts with Select Committee Jan. 9 meeting (7:30pm in Town Hall)...
The Board of Selectmen, at Jan 4. meeting, established a Committee that consists of nine members. Click HERE for more.


In the past...
No reflection on quality or feasibility of School Plan or Planners..."Select Committee..." formed by Board of Selectmen June 15, 2000 to work on the problem.  Town needs to come up with solution to septic disposal problem in a different way than architect/planners had been directed. "GROUNDWATER SUPPLY FEASIBILITY" COMPLETED:  click here for link.


MOST RECENT BUILDING COMMITTEE MEETING NOT ATTENDED; "About Town" notes, however, that the Chair. of that Committee abstained from Select Committee vote that picked an engineering firm to study non-sewer alternatives at a later date.
PREVIOUSLY AT THE BUILDING COMMITTEE:  AUGUST 17 AT 7:15pm (TOWN HALL MEETING ROOM) still going strong at 10:30pm ("About Town" at the Selectmen's Meeting:  other Towns' experiences with school construction [representatives present] on AGENDA.


About Weston skips Selectmen's discussion of insurance policies, attends instead...
BOARD OF EDUCATION SPECIAL MEETING JUNE 22, 2000:
What was particularly interesting about this Special Board of Education meeting called to deal with "Handling Enrollment Growth" was the emergence of pre-school parents (very angry at the Board of Education) who were concerned about the possible loss of their entitlement of modified full day kindergarten. They and others spoke during "Public Comment."  Points made were:
Breezing through the agenda, "Dr. T" (Dr. Len Tomassello, Hurlbutt) then addressed the Board regarding solutions he and his team had found.  In summary:

The assumptions made were that modified full day was still the best--cited Claire Gold report re: early intervention.  Link here to conclusions of the report:  Conclusions printed here.

DR. T'S TEAM'S ASSUMPTIONS:

  1. there will not be more than this year's 5 new portables (in place at the Weston Middle School) allowed
  2. current level of service for all grades
  3. IF level of service to children must be curtailed, THEN only 4th grade would be exempt.
PERSONNEL:  Kindergarten teachers must not be forced to teach two sections of 24 children each in the same day
FACILITIES:  East House for Kindergarten and first grade only;  South and North House should mix grades 1-2-3- and 4. NOTE:  if the Westport-Weston Health District could be prevailed upon to permit more portables on the Hurlbutt site, a place for 5 more portables between the Library/North House and East House and/or South House would make life easier for the school children...because without more new space in 2001-2002 school year alternative OPTIONS will have to be considered.

OPTIONS MUSIC:

OPTIONS ART: PHYSICAL EDUCATION (P.E.): COMPUTER LAB: LIBRARY: QUESTIONS FROM THE BOARD:
  1. can we go back to WWHD to get more portables? (no answer)
  2. we are at a crossroads (self-evident)
  3. educators want to move ahead with improving education (good luck)
  4. what do we do next year? (same drill as this year)
  5. will we look off-campus for kindergarten solution? (already on it)
  6. modular construction k-2 at Heady site?
  7. is it reasonable to assume that Heady can be used?
  8. could we place a lot more pressure on other Boards?
  9. we should have had contingency plans (in retrospect)...hard choices
Departing school board member remarked that political decisions are made in crisis...there are no new ideas...Board of Education has no power to make its plans come to fruition because it never considers the cost of anything...no one wants to share a high school...the best thing that has happened recently is hiring Dr. Shaner, who will lead.  Financial decisions and the septic problems will over-shadow others.

Meeting ran from 7:45pm to 9:30pm.

NEXT BOARD OF EDUCATION MEETING JULY 17 at 7:30pm.



CTDEP SPEAKS...
The other shoe drops...found on the Weston Board of Education WEBpage is commentary from the Superintendent indicating that via a telephone call the day after the May 25 PUBLIC HEARING, the CTDEP representative is quoted as having said "...things 'aren't that drastic yet'" regarding limiting the number of students at Hurlbutt.  CTDEP goes on to say that we need to decide by September a temporary solution to the septic issue (i.e. pump and haul).  "About Town" would like to know whether the CTDEP indicated which September they were planning to act...


1. Master Schedule changed...Selectmen appointed Ad Hoc "Select Committee" for 90 day+ stint to come up with new ideas, using data collected by Fuss&O'Neill as well as other Town studies, thus reworking plans for Septic/Sewer already presented;  Planning and Zoning, Conservation, Board of Education and Building Committee plus five citizens were named June 15...worked during summer vacation...link here to information about progress and re-appointment of Select Committee:SEWAGE TREATMENT COMMITTEE

2.THE FINAL SCHOOL FACILITIES PLAN (now on hold) TEXT AND DETAILS...
3. MAP OF 100+ ACRE CAMPUS FOUND HERE!



Building Committee June 8 at 7:30 in Town Hall:

Five members of the Building Committee (two others absent) plus two members additional making up the School Building Committee (Superintendent of Schools and member of the Board of Education) met to discuss trips upcoming to architects' (Jeter, Cook and Jepsen; Tai Soo Kim and Fletcher-Thompson) offices and school buildings they had designed.

Another item on the agenda was a discussion of sewer/septic issue and the Building Committee's role in the future on this topic.  The Chair. was appointed to sit on the new "Select Committee…" that will be studying sewer options over the next 90 days.  A spirited discussion took place about what the impact of a tiny sewer line to just the Schools and Town Hall would be--and if indeed the implications for development density would be almost nil, as some members of the Building Committee purported.  Members of the Building Committee believe that "a tiny sewer line bringing only 60,000+ gallons of effluent from Weston to the Norwalk treatment plant" (as described in Fuss&O'Neill report) thus setting a limit on development) would permit Weston to then say no to affordable housing applications along the route of the sewer.

Members of the public were invited to participate in this meeting, and it was also discussed whether inviting AVALON, affordable housing construction company, to propose an example of how an affordable housing scheme might work for Weston would be a good idea.



Selectmen OK $765,000 for architects' conceptual drawings;  school construction projects still alive...architect interviews continuing?  It is a puzzlement, but we are apparently interviewing architects if and when we figure out what we want/need/can actually follow through with...


SELECT COMMITTEE ON SEWAGE TREATMENT now appointed and first meeting took place Monday, June 19, 2000 at 7:30pm in Town Hall;  tent. next two meetings:  June 28 and July 6., 7:30pm in Town Hall...


If there had been a Town Meeting on sewer/septic...
Those eligible to vote: if not registered to vote in the Town of Weston, you may still qualify to vote at Town Meeting (and at this Referendum) IF you are a U.S. citizen who is over the age of 18...who own $1000 in taxable property on the Town of Weston's Grand List...and all registered voters in the Town of Weston are qualified to vote at Town Meeting!
ABSENTEE BALLOTS FOR TOWN MEETING REFERENDUM OK, according to Secretary of the State.


SCHOOL BUILDING COMMITTEE INTERVIEWS, MAY 8 and 9, 2000,TOWN HALL MEETING ROOM

Town Hall Meeting Room, May 8, 2000, 7pm to 9:45pm;  May 9, 2000 report from indirect sources;  NOTE: as of June 14, 2000, this process is rolling along, with final three firms being visited plus site visits to examples of their work.

NOTE:  it is the intention of the Building Committee to check out references and projects by these architects;  they may invite firms back for more questions; need to visit examples of work and offices.

First two interviews completed Monday - both firms are interesting yet different...three more architects to be heard from in this round...
The Building Committee and its three new advisory members interviewed Jeter, Cook and Jepson and Tai Soo Kim, 2 of 5 "semi-finalists" for Weston's projected $70 million suggested schools project.  (The "final" decision is to be made by the Board of Selectmen.)
Monday's interview schema was divided into three sections--first the firms gave background about themselves, then they discussed their ideas in response to the RFP and then the Building Committee asked questions.  The same questions were asked of each applicant (unless answers were already provided during earlier parts of the presentation).

JETER, COOK & JEPSON (as "AboutTown" heard it)
"We are the only firm large enough to meet the schedule" and "very large project" were their comments on Weston's School Plan (all in one phase).  A YR2002 completion will require three teams, multiple consultants, 35 full time people;  Weston should "maximize reimbursement."  Jeter, Cook said "they don't reinvent the wheel."

In order to meet the schedule Jeter, Cook suggests local review by local building inspector (instead of waiting for the State Department of Education team) and construction of 3-4-5 school first with an eye to using it as "swing space."

QUESTION:  What if the schedule is more spread out?
ANSWER:  It would be better--Jeter, Cook and Jepson do not think building a gym and auditorium can be done in 3 months (didn't indicated which school).
QUESTION:  If you stretch out the project, what will this do to materials costs?
ANSWER:  Based on the present economy, costs can only go up--but reference was inserted at this point to downgrades being made in design standards because of absence of proper, long-term materials (standards for schools become more like those for commercial structures and not public buildings).
QUESTION:  In this tight ("aggressive") schedule, how will there be time to get input from school staff?
ANSWER:  ?
QUESTION:  How about contingencies?
ANSWER:  Not high enough (suggests 10% rather than 5%) in parts of program that involve rehab of older structures.
QUESTION:  Are you planning on retaining consultants for energy conservation?
ANSWER:  Yes
QUESTION:  What is your work schedule like now?
ANSWER:  No problem - they are a big firm (64 years in business).

WORK IN AREA:  North Avenue schools (Staples additions and Middle School), Westport.

TAI SOO KIM (as "About Town" heard it - same questions)
The next firm is a consortium of creative designers and practical implementers.  This firm had been a finalist for the School Plan exercise, contract having gone to O,R&L.  Tai Soo suggested that the one-way road "loop" should be redirected in front of the new 3-4-5 school location to avoid wetland crossing altogether (with intersection at School Road [west end] coming to a "T" and not creating a dangerous traffic situation near Weston Road.

This company has been in business for close to 30 years.  Comments by "business" partner in intro: "Unique, creative solutions" - "Stimulating children's minds" - "Not cookie-cutter work."  A full examination of topos and environmental info as well as traffic solution re-examination was done in this, the "best response" (as the Chair. stated referring to the way Tai Soo had followed the instructions in the RFP).  "Design" partner said, simply, that this type of school construction work demanded "...need to transform the school."  As an example of what was meant by this remark, he pointed to the entrance to both the high school and the middle school - cold, distant, formal stairways...off-putting (my interpretation of his message)."

Tai Soo further stated that there was a need to stretch out the project (altho' they were prepared to do what we wanted) - "don't commit all up front."  "Forty-million dollars for the new elementary plus" some other parts of the project should be all Weston should attempt, according to this architect.

WORK IN AREA:  Cider Mill School (elementary and 3-4-5 total of 1100 students in Wilton)
-------------------------------------------------------------------------------------------------
WEDNESDAY INTERVIEWS NOT COVERED BY ABOUT  WESTON - BUT TWO RELIABLE SOURCES REPORT THAT  FLETCHER - THOMPSON OF BRIDGEPORT WILL BE INCLUDED IN FINAL "CUT"-- PRELIMINARY THREE CHOICES FOR VISITS ARE (NUMBER MIGHT VERY WELL BE CHANGED/ENLARGED AFTER COMMITTEE VISITS EXAMPLES OF PREVIOUS WORK AND SITES AND OFFICES OF FIRMS NOT FAMILIAR TO BUILDING COMMITTEE):  JETER,COOK & JEPSON;  TAI SOO KIM;  FLETCHER - THOMPSON.

CJNA WORKING CLOSELY WITH THE BOARD OF SELECTMEN TO GET EDUCATION SPECIFICATIONS READY FOR JUNE 30 DEADLINE (WITHOUT MEETING THIS DEADLINE NO PROJECT, NO MORE SCHOOL CONSTRUCTION WILL BE ERECTED FOR ONE EXTRA YEAR!!!).



Selectmen OK ED SPECS FOR State Funding by June 30
Board of Selectmen (May 4 meeting) approved extra payment ($19,200) for School Planner to draw up education specifications...Ed Specs for four part Plan.  Four buildings and areas around them will be separate applications.  For example:  the new 3-4-5 building and attendent fill, paving, fields is one;  the high school project plus moving School Road is two;  the Middle School auditorium and renovations plus loop road is three;  Hurlbutt renovations and School Road entrance is four.  So easy to explain! (These are my guesses--not confirmed what the four separate projects will actually be.)


MAY 18 and May 25 Dates to note...
On May 18, 2000 at 7:30pm in the Weston Library Fuss&O'Neill will present their draft plan for sewers/septic to Town of Weston Boards and Commissions.  The public is invited...but not to speak.  On May 25, 2000 at 8pm in the W.H.S. auditorium, there will be a PUBLIC HEARING on this same proposal.  On June 1, 2000 (est.) at the Board of Selectmen, a decision will be made by that Board, and a recommendation will be made to the Board of Finance and then to Town Meeting...more dates for more meetings to come...see above.


For a full run-down of what happened at the PUBLIC HEARING on April 27, go to...
Board of Selectmen/Public Meeting Notes
Friendly visit to Conservation Commission for School Planner, Superintendent of Schools...Go to Conservation Commission


RESPONSES RECEIVED OFFICIALLY TO RFP Monday, April 24 at 11am in Town Hall; only the name and address revealed at this time.

Nine (9) architectural firms repond to RFP and fivemake it through successfully.  Making it to the next level are the architectural firms in red and underlined--the first "cut" by Building Committee was:
1.  Wiles and Associates (Bridgeport)
2.  Fletcher-Thompson (Bridgeport)
3.  DiCarlo & Dahl (Hamden)
4.  Schoenhardt Associates (Simsbury)
5.  Friar Associates (Farmington)
6.  CJNA - Charles J. Nafie & Associates - (New York City)
7.  C.J. Lawlor (West Hartford)
8.  Tai Soo Kim (Hartford)
9.  Jeter, Cook and Jepson (Hartford)
 

On Tuesday, after the Building Committee had met, "About Town" looked through all nine responses to the RFP...all references to price/cost were removed (so that this matter can remain confidential and be negotiated).



Planning and Zoning Commission asked in letter from First Selectman to review School Plan "at next meeting"--which was April 17;  the review - an 8-24 report - will begin when the Town re-submits the Plan (Town Attorney withdrew it Monday, April 17).  For more: Public Meeting Notes


Pre "Walk through" held Thursday, April 13 at 10am in Town Hall;  lots of A&E firms show up...RFP due April 24;  Building Committee to review the responses May 1 and, if necessary, May 2, 2000 at 7pm in Town Hall Meeting Room.


SCHOOL FACILITIES PLANNING COMMITTEE (F.P.C.):  Monday evening, March 27, 2000 at 7pm in the Meeting Room at Weston Town Hall...voted in favor of recommending 4A, Scheme 'A' (same language as below);  of the voting members of the F.P.C. who were present, none were opposed.  See PUBLIC MEETING NOTES:
Public Meeting Notes (Facilities Planning)


BOARD OF EDUCATION VOTED UNANIMOUSLY TO RECOMMEND TO THE BOARD OF SELECTMEN...OPTION 4A (3-4-5 across from Board of Education Headquarters) and PHASING SCHEME 'A' (all in one stage) at the Special Meeting on March 23, 2000.  For a blow by blow description of this brief meeting, click below:
Public Meeting Notes (scroll down to Board of Education)
VIEW FINAL SCHOOL PLAN ON-LINE

(click here)