Click above for great website.

R O U N D A B O U T S

The research. 
Even on Whidbey Island!  And at Greenwich-Stamford border...and elsewhere in CT!

AASHTO GREEN BOOK

Proposal in Bristol - UK.



Hearing Set For Roundabout For Four Corners 
DAY
By Paul Petrone 
Published on 6/14/2009

The state Department of Transportation will hold a public meeting Wednesday at 7 p.m. to give Salem residents a chance to voice their opinions on the proposed roundabout for Salem Four Corners.  The roundabout, which would replace the current lighted intersection at Routes 85 and 82, would be a one-lane hybrid design, according to Will Britnell, the DOT's project manager.  Currently, that intersection is one of the more dangerous in the state, Britnell said. By installing the roundabout, he hopes it will make the area dramatically safer.

”The studies show that roundabouts reduce accidents by 39 percent, injuries by 76 percent and fatalities by 90 percent,” Britnell said.

Britnell also points out that similar studies have shown that traffic moves faster through roundabouts than at intersections, reducing carbon emissions by 30 percent.  While the roundabout would primarily have one lane, he said, there would be a separate lane for cars driving east on Route 82 and turning right onto Route 85, a common route for people coming off Route 11.  There would also be a lane installed for commuters driving north on Route 85, according to Britnell. The roundabout would widen to two lanes until it unloads traffic on Route 85 north.

Three buildings would be removed to complete the roundabout, which would be located west of the original intersection, including the former Bad Boyz Toyz building and the adjacent vacated white house. The area will be cleared and converted into an open field leading up to the bank of Harris Brook.  The third building that would be demolished would be the former general store in the Salem Town Marketplace, which is now Gin Seng Spa and Massage Parlor.

Gin Seng Spa would be forced to move, but the transportation and relocation fees would be paid by the state.  Britnell expects the project, which is still in the conceptual design phase, would be built in 2012 and cost $2.75 million, all of which would be paid for by the federal government.

If there are no major, valid concerns brought up at the meeting by residents, the project will move from the conceptual design phase to the formal design phase, according to Britnell.  




Damage is apparent at a traffic circle at South Water Street and Mead Avenue, which Byram residents say is repeatedly damaged by trucks because of poor design. (Keelin Daly/Staff photo)
Not exactly a roundabout...
Byram residents to town: Fix our traffic circle
Greenwich TIME
Eye on Greenwich
Posted: 09/09/2009 05:40:21 PM EDT

This wheel may need re-inventing.

A traffic circle built about a year ago at South Water Street and Mead Avenue in Byram is drawing criticism from residents, who say its flawed design cannot accommodate large trucks that frequently cause damage to the roundabout.

"This happens constantly," Susan Frano, who lives nearby, wrote in an e-mail to Eye on Greenwich.

Frano said it's been several months since a truck destroyed part of the curb of the traffic circle, where the town has since put up some orange cones and sawhorses.

Amy Siebert, the public works commissioner, said the town has located the culprit truck's owner and is waiting for his insurance to pay for the damage.

"Yes, we know there was some damage from a rogue truck," Siebert said. "We fortunately caught him."

Siebert contested claims that the traffic circle was poorly designed, however, saying it was never intended to accommodate all trucks.

"We do get some yahoo drivers," Siebert said. "It's up to these truck drivers that come with certain sorts of vehicles to take proper care when they're going through intersections."

Siebert said she would love for a neighborhood group to assume responsibility for the beautification of the center of the traffic circle.

Byram resident Chris Antonik echoed Frano's concerns about the traffic circle.

"When they built it, we knew that it wouldn't work," Antonik said. "That really disgusted me. It was a waste of our taxpayers' money."



Roundabout causes stir among residents
Stamford ADVOCATE
By Neil Vigdor
Article Launched: 06/02/2008 01:00:00 AM EDT

GREENWICH - Designed to ease traffic congestion from a new housing development, a roundabout on Havemeyer Lane is drawing complaints from residents.  The roundabout is unsightly and may create backups on Havemeyer, which straddles the Stamford-Greenwich border, some residents say.

"We have been getting calls about it - did I know what was going on? Why did we do this?" said Diane Fox, Greenwich town planner.

Stamford and Greenwich officials agreed on the design as part of the settlement of a lawsuit involving the two municipalities over Palmer Hill, a 195-unit townhouse and condominium development on the former Cuisinart property at 77 Havemeyer Lane, Fox said.  The developers are Buckingham Partners of Haddonfield, N.J., and Sun Homes of Pawling, N.Y.

"There's been a lot of history on this," Fox said. "It wasn't done quietly, by any means."

Officials were concerned about vehicles entering the road from the development and speeding, she said.

"This was felt to be a good traffic-calming device," Fox said. "It certainly forces us all to slow down."

Installed about two weeks ago, the roundabout collects traffic from Havemeyer Lane to the north and south, North Ridge Road to the west and the entrance of the housing development in Stamford to the east.  Sam Romeo, a neighborhood leader, said drivers will bypass Havemeyer Lane for the more residential Florence and Old Orchard roads to avoid the roundabout.

"It's an absolute nightmare," Romeo said. "Even my wife, we had to get out to the Post Road, she said, 'You're not going through the war zone?' I think it's a big mistake."

Bob Dale, managing partner for Buckingham Partners, said the roundabout is under construction and won't be completed for about two weeks.  A traffic light will be installed at Havemeyer Lane and Palmer Hill Road during the summer, Dale said. Developers were sensitive to effects on the neighborhood, he said.

"I think we've actually worked well with the neighbors," Dale said.

Selling for $500,000 to about $1 million, the units will be ready for occupancy in July, Dale said. Forty of the 195 units have been sold.  Greenwich and Stamford will be responsible for plowing snow from the roundabout, though Havemeyer Lane often is cleared by Greenwich highway employees through an agreement with Stamford.  Fox said Greenwich officials have limited authority over Havemeyer Lane because most of the street is in Stamford.

"People may think we own Havemeyer Lane. We don't. Only up to a certain point," Fox said.

Havemeyer residents back roundabout
Greenwich TIME
By Neil Vigdor, Staff Writer
Published March 28 2006

In a show of hands at a public hearing last night, a majority of Havemeyer Lane area residents signaled their support for a town-designed roundabout for the busy artery to help mitigate the impact of a new housing development.

Unveiled by the town's traffic engineer and planner at a special meeting of the Board of Selectmen, the roundabout would collect traffic from Havemeyer Lane to the north and south, North Ridge Road to the west and the entrance of a 195-unit housing development in Stamford to the east.

 The planned development, which is on the site of the former Cuisinart property at 77 Havemeyer Lane, has gained zoning approval from Stamford but has been tied up in litigation with Greenwich. Town officials, uncertain of the development's impact on the surrounding streets, want to have a hand in any changes to the traffic pattern.

"The roundabout would seem to be a very good safety measure," said Kathleen Saxon, a Northridge Road resident.

Saxon, like many of the 30 to 40 residents who attended last night's public hearing, called on officials to modify the design to include a one-way traffic restriction on her section of North Ridge Road so that cars would not be able to enter the cross-street from Havemeyer Lane.

But residents of some surrounding streets said the one-way restriction might increase traffic on their blocks, a warning echoed by town officials.

"Just remember, traffic is like water," Selectman Peter Crumbine said. "It's going to go somewhere."

First Selectman Jim Lash said the town would use the input from residents during its negotiations with the developer, Buckingham Starwood, in the legal case.

"We don't have a lot of leverage," said Lash, who cautioned that the roundabout design had to be accepted by the developer, as well as Stamford zoning officials. "In the end, this is in Stamford."



T R A N S P O R T A T I O N    R E S E A R C H

COUNTING ROUNDABOUTS: A MODEL TO OBTAIN DETAILED ROUNDABOUT TURNING MOVEMENTS

Accession Number:

00822702

Record Type:

Component

Language 1:

English

 

Abstract:

To determine whether a roundabout or an intersection would work best at a particular location, it is important to know the number of vehicles making each turning movement. Methodologies have been developed for analyzing roundabout levels of service without knowing the detailed turning movements. To analyze whether a roundabout or signalized intersection would work better in a specific location, however, the detailed turning movements are needed. A methodology to determine existing turning movements at roundabouts with minimal labor is presented. Using only four persons, a typical four-leg roundabout can be counted, and all turning movements (including U turns) can be accurately estimated. The study to update the Master Transportation Plan of Abu Dhabi -- the Capital of the United Arab Emirates -- provided the opportunity to develop and test this approach. The roundabout counting methodology starts with procedures to count traffic volumes, including identification of specific movements to be counted. The counts are then entered into a model, which initially estimates all turns using percentages of vehicles exiting at various locations. The model then iteratively adjusts the turns until all entry and approach values match the counted values. Adjustment coefficients have been added into the process and calibrated, and the model has been successfully applied to obtain reliable turning movement estimates for three-, four-, and five-leg roundabouts. The model has been tested using data where all turns were known in advance and has proven to be quite reliable.

Supplemental Notes:

This paper appears in Transportation Research Record No. 1769, Pavement Management, Monitoring, and Accelerated Testing.

TRIS Files:

HRIS

Pagination:

p. 103-112

Authors:

Al Kathairi, A S; Mufti, R K; GARIB, A M; Williams, B F; Bierce, E

Features:

Figures (9); Tables (1)

 

Monograph Info:

See related components

Corporate Authors:

  • Transportation Research Board
    500 Fifth Street, NW
    Washington, DC 20001 USA

Availability:

  • Transportation Research Board Business Office
    500 Fifth Street, NW
    Washington, DC 20001 USA

ISBN:

030907231X

Publication Date:

2001

Serial:

Transportation Research Record
Issue Number: 1769
Publisher: Transportation Research Board
ISSN: 0361-1981

 

Index Terms:

Estimates; Level of service; Mathematical models; Methodology; Reliability (Statistics); Roundabouts; Traffic counting; Turning traffic; Abu Zaby (United Arab Emirates)

Subject Areas:

H55: TRAFFIC FLOW, CAPACITY AND MEASUREMENTS
I72: Traffic and transport planning